Introduction to Offshore

Offshore, depending on size and water depth, a whole range of different structures are used. In the last few years, we have seen pure sea bottom installations with multiphase piping to shore and no offshore topside structure at all.

Offshore Oil and Gas Production Facilities
Offshore Oil and Gas Production Facilities (on photo: Offshore oil and gas company in the UAE; constructionweekonline.com)

Replacing outlying wellhead towers, deviation drilling is used to reach different parts of the reservoir from a few wellhead cluster locations.

5 most common offshore structures are described below:

  1. Shallow Water Complex
  2. Gravity Base
  3. Compliant Towers
  4. Floating Production
    • Floating Production, Storage and Offloading (FPSO)
    • Tension Leg Platform (TLP)
    • SPAR
  5. Subsea Production Systems

1. Shallow Water Complex

Ekofisk Norway's first producing field
Ekofisk was Norway’s first producing field and is also one of the largest on the Norwegian continental shelf. Production started in 1971. With the projects now under development, the lifetime of the field is prepared for production towards 2050.

Characterized by a several independent platforms with different parts of the process and utilities linked with gangway bridges.

Individual platforms will be described as:

  • Wellhead Platform,
  • Riser Platform,
  • Processing Platform,
  • Accommodations Platform and
  • Power Generation Platform.

The picture shows the Ekofisk Field Centre by Phillips petroleum. Typically found in water depths up to 100 meters.

Go to Index ↑


2. Gravity Base

The world’s largest GBS platform, the Troll A during construction
The world’s largest GBS platform, the Troll A during construction

Enormous concrete fixed structures placed on the bottom, typically with oil storage cells in the “skirt” that rests on the sea bottom.

The large deck receives all parts of the process and utilities in large modules. Typical for 80s and 90s large fields in 100 to 500 water depth.

The concrete was poured at an at shore location, with enough air in the storage cells to keep the structure floating until tow out and lowering onto the seabed.

The picture shows the world’s largest GBS platform, the Troll A during construction.

Go to Index ↑


3. Compliant Towers

Compliant tower - Oil and gas production facility
The compliant tower design was chosen for its ability to withstand hurricane conditions and operate in depths of 2,000ft (610m) // Photo by offshore-technology.com

Compliant towers are much like fixed platforms. They consist of a narrow tower, attached to a foundation on the seafloor and extending up to the platform.

This tower is flexible, as opposed to the relatively rigid legs of a fixed platform. This flexibility allows it to operate in much deeper water, as it can ‘absorb’ much of the pressure exerted on it by the wind and sea.

Compliant towers are used between 500 and 1000 meters water depth.

Go to Index ↑


4. Floating Production

Helix Producer I DP2 monohull floating production unit
The Helix Producer I DP2 monohull floating production unit is designed to produce hydrocarbons and export to shore via pipeline or tanker.

Floating production, where all topside systems are located on a floating structure with dry or subsea wells.

Some floaters are:

4.1 Floating Production, Storage and Offloading (FPSO)

Typically a tanker type hull or barge with wellheads on a turret that the ship can rotate freely around (to point into wind, waves or current). The turret has wire rope and chain connections to several anchors (position mooring – POSMOR), or it can be dynamically positioned using thrusters (dynamic positioning – DYNPOS). Water depths 200 to 2000 meters.

Common with subsea wells. The main process is placed on the deck, while the hull is used for storage and offloading to a shuttle tanker.

May also be used with pipeline transport.

Go to Index ↑

4.2 Tension Leg Platform (TLP)

Tension leg platform
The hull for Shell’s deepwater tension leg platform Brutus arrived at Aker’s Ingleside yard in Texas (the integration site) in January 2001.

A Tension Leg Platform (TLP) consists of a structure held in place by vertical tendons connected to the sea floor by pile-secured templates. The structure is held in a fixed position by tensioned tendons, which provide for use of the TLP in a broad water depth range up to about 2000 m.

Limited vertical motion. The tendons are constructed as hollow high tensile strength steel pipes that carry the spare buoyancy of the structure and ensure limited vertical motion.

A variant is Seastar platforms which are miniature floating tension leg platforms, much like the semi submersible type, with tensioned tendons.

Go to Index ↑

4.3 SPAR

Floating platform - Neptune SPAR
Similar to an iceberg, the majority of a SPAR facility is located beneath the water’s surface, providing the facility increased stability

The SPAR consists of a single tall floating cylinder hull, supporting a fixed deck. The cylinder however does not extend all the way to the seafloor, but instead is tethered to the bottom by a series of cables and lines.

The large cylinder serves to stabilize the platform in the water, and allows for movement to absorb the force of potential hurricanes. Spars can be quite large and are used for water depths from 300 and up to 3000 meters.

SPAR is not an acronym, but refers to its likeness with a ship’s spar. Spars can support dry completion wells, but is more often used with subsea wells.

Go to Index ↑


5. Subsea Production Systems

Subsea separation system
The Marlim subsea separation system on Petrobras’ largest field in the Campos Basin separates heavy oil, gas, sand and water. The system debottlenecks the floating production facility and increases production by removing unwanted water from the production stream at the seabed.

Subsea production systems are wells located on the sea floor, as opposed to at the surface.

Like in a floating production system, the petroleum is extracted at the seafloor, and then can be ‘ tied-back’ to an already existing production platform or even an onshore facility, limited by horizontal distance or “offset”.

The well is drilled by a moveable rig and the extracted oil and natural gas is transported by undersea pipeline and riser to a processing facility. This allows one strategically placed production platform to service many wells over a reasonably large area.

Subsea systems are typically in use at depths of 7,000 feet or more, and do not have the ability to drill, only to extract and transport. Drilling and completeion is performed from a surface rig. Horizontal offsets up to 250 kilometers, 150 miles are currently possible.

Go to Index ↑

Reference: Oil and gas production handbook – ABB ATPA Oil and Gas

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical engineering guides, research studies and much more! It helps you to shape up your technical skills in your everyday life as an electrical engineer.
More Information
author-pic

Edvard Csanyi

Electrical engineer, programmer and founder of EEP. Highly specialized for design of LV/MV switchgears and LV high power busbar trunking (<6300A) in power substations, commercial buildings and industry facilities. Professional in AutoCAD programming.

6 Comments


  1. Gbadegesin olawale nurudeen
    Jan 13, 2019

    15 oladire street of Isale Aruba ifako ijaye Lagos Nigeria.

    I’m a mechanical and electrical engineering, engineering is very interesting wich I so mush have a passion for, I have work in different kind of fied as a Technisian which I repair and service and installation both mechanical and electrical , I can say that I have about 17years experience in the feid


  2. Okafor Onyeka Charles
    May 01, 2015

    Engineering is a very interesting discipline


  3. Benz AC
    Oct 26, 2014

    Hope you guys post what’s the actual work of an electrical engineer in an offshore oil and gas production because i’m now in my last year in electrical engineering and i want some insight what would they actually do there cause that’s my dream job..


  4. Byju MS
    Aug 11, 2014

    Excellent,very much useful


  5. Janet Adams
    Jun 24, 2014

    I would like to find Operations Engineers with Offshore experience. The candidate should be able to work independently and have 5 years + experience. Platform is in the Gulf of Mexico.


    • Violet Deresoma
      Sep 12, 2019

      Do you have any job placement for an oil and gas production officer with seven years experience.

Leave a Comment

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

77  +    =  eighty

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

Subscribe to Weekly Newsletter

Subscribe to our Weekly Digest newsletter and receive free updates on new technical articles, video courses and guides (PDF).
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge