Power distribution

Power distribution systems are used in every residential, commercial, and industrial building to safely control the distribution of electrical power throughout the facility. Most of us are familiar with the power distribution system found in the average home.

Switchboard Construction - Siemens Basics
Switchboard Construction – Siemens Basics (photo credit: elektro.info.pl)

Power purchased from a utility company enters the house through a metering device. The power is then distributed from a load center to various branch circuits for lighting, appliances, and electrical outlets.

The role of a switchboard is to divide the main current provided to the switchboard into smaller currents for further distribution and to provide switching, current protection, and metering for these various currents.

Although this applies to all switchboards, the voltages and currents involved vary with the size of the application.

There are multiple elements that make up a switchboard. Included in the list of elements are a frame, buses, overcurrent protective devices, service metering, and outer covers.


Switchboard Frame

The frame of the switchboard houses and supports the other components. The standard Siemens switchboard frame is 90 inches high and 32 or 38 inches wide. An optional height of 70 inches with widths of 32, 38, or 46 inches is also available. Siemens switchboards have a depth measurement ranging from 20 to 58 inches.

The frame of the switchboard
The frame of the switchboard

Bus

A bus is a conductor or set of conductors that serves as a common connection for two or more circuits. NEC® article 408.3 states that bus bars shall be located so as to be free from physical damage and shall be held firmly in place.


NEMA Phase Arrangement

Bus bars are required to have phases in sequence so that an installer can have the same fixed-phase arrangement in each termination point in any switchboard. This is established by NEMA (National Electrical Manufacturers Association). If a non-NEMA phase sequence is used, it must be marked on the switchboard.

Unless otherwise marked, it is assumed that bus bars are arranged according to NEMA. The following diagram illustrates accepted NEMA phase arrangements.

Buses are mounted within the frame. Horizontal bus bars are used to distribute power to each switchboard section. Vertical bus bars are used to distribute power via overcurrent devices to the load devices. Bus bars are made of tin-finished aluminum or silver-finished copper. Bus bars may either be temperature rated or current density rated.

The current density rating specifies the maximum current per square inch of a bus bar cross section.

Buses are mounted within the frame, vertical and horizontal
Buses are mounted within the frame, vertical and horizontal

The following rear view drawing of a switchboard illustrates vertical and horizontal bus bar connections. The vertical phase bus bars appear to be in reverse order because they are viewed from the rear, but are in the proper NEMA order as viewed from the front.

A bus connector makes a mechanical and electrical connection between a vertical bus bar and its corresponding horizontal bus bar.

In this drawing the connector can be clearly seen on the neutral bus. Compression lugs provided on this switchboard accept properly sized incoming power cables.

Vertical and horizontal bus bar connections
Vertical and horizontal bus bar connections

Splice Plates

Splice plates are used to join the horizontal bus bars of adjoining switchboard sections, as illustrated in the following rear view drawing. To make additional distribution sections easier to install when they are needed, the horizontal bus is extended and pre-drilled to accept splice plates.

A new section is set flush against an existing section. The old and new sections are connected together with splice plates.


Through-bus

The extended horizontal bus is also referred to as through-bus. Because the load requirements in downstream distribution sections are generally less than in upstream service sections, the capacity of the through-bus is tapered, or reduced, downstream as the load falls off.

The through-bus is tapered to a minimum of one-third the ampacity of the incoming service mains.

Full-capacity, or non-tapered, through-bus is available as an option. The ampacity of non-tapered through-bus remains constant throughout the switchboard.

Rear view drawing - slice plates
Rear view drawing – slice plates

Overcurrent Protective Devices

Operator components are mounted on the front side of the switchboard.

This includes overcurrent protective devices, such as circuit breakers and disconnect switches. These devices are mounted to the bus bars using straps connected to the line side of the devices.

Overcurrent protective devices, circuit breakers and disconnect switches
Overcurrent protective devices, circuit breakers and disconnect switches

Outer Covers

Cover panels are installed on the switchboard so that no live parts are exposed to the operator. The front cover is referred to as the dead front. The panels are also used as trim to provide a finished look to the switchboard.

A product information label identifies the switchboard type, catalog number, and voltage and current ratings.

Pictorial Diagram

Simplified drawings, such as one-line, block, or pictorial diagrams are often used to show the circuits associated with a power distribution system. For example, the following pictorial diagram shows a two section switchboard.

Reference: SiemensBasics of Switchboards

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical engineering guides, research studies and much more! It helps you to shape up your technical skills in your everyday life as an electrical engineer.
More Information
author-pic

Edvard Csanyi

Electrical engineer, programmer and founder of EEP. Highly specialized for design of LV/MV switchgears and LV high power busbar trunking (<6300A) in power substations, commercial buildings and industry facilities. Professional in AutoCAD programming.

14 Comments


  1. Ratheesh
    Feb 20, 2019

    Dear Sir,

    We need to make one switchboard with 3 X 30KW generators, and it have load sharing controller.How to design busbar for this configuration. 415V,50Hz, 3 Phase with neutral.


  2. Wong Chon Foong
    Sep 21, 2018

    Sir, any recommendation how to fabricate withdrawal type switchboard?…


  3. Atiq
    Oct 24, 2017

    dear
    i have a some issues starting of 1.2 MW 6.6 kv motor.we used soft starter for starting.
    6 MW gas turbine generator for generation.
    issued… when start the motor then voltage drop the LV Bus Bar and trip the LV ACB.


    • Vishal
      Jul 06, 2019

      1. What is behaviour of generator during motor start?
      2. What is base load while starting motor?


  4. Schaffhouser Electric
    Feb 03, 2016

    Electrical construction encompasses the installation, design, wiring, testing and maintenance of electrical systems and equipment. This type of work is critical for the safety of commercial and industrial facilities, and requires a strong skillset of electrical and wiring expertise.


  5. Le Nguyen
    Dec 18, 2014

    We have new inquiry for Electric items. Could you please provide us email address to contact.
    Thank you.


  6. adnansajjadi
    Sep 26, 2013

    Hi, Sir i have a question regarding the calculation of CB in switchboard by witch formula we are able to calculate the value of switchboard? i really be much appreciated you if you help me .


    • Edvard
      Sep 26, 2013

      You must know rated current of the load on each circuit breaker. This leads you to the load, the information you must have (or calculate) according to the customer’s inputs.


  7. glentaught
    Oct 23, 2011

    another question sir.. about to the construction…what material are the board to be made, and what type of framework is to be use?


  8. glentaught
    Oct 23, 2011

    i have a question to you sir… is this switchboard to have remote mechanical or remote electrical control? why?


  9. glenn
    Oct 23, 2011

    i have a question to you sir… is this switchboard to have remote mechanical or remote electrical control? why?


    • Edvard
      Oct 23, 2011

      Well, it must have either mechanical or electrical control. if you want to remote close or open CB’s contacts (with open and closing coil) from some distance place like control center (with SCADA, etc.), then you must have motor spring to charge it.

      If you don’t have any remote control, then you use just mechanical control on the circuit breaker (open/close button).


  10. hamayun khan
    Apr 12, 2011

    thats very good


    • Edvard
      Jun 07, 2011

      Thank you Khan! Glad you like it, this SIEMENS’s guide is really good.

Leave a Reply to Le Nguyen

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

5  +  five  =  

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

Subscribe to Weekly Newsletter

Subscribe to our Weekly Digest newsletter and receive free updates on new technical articles, video courses and guides (PDF).
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge