Search

Premium Membership ♕

Limited Time Offer: Save 15% on PRO Plan with discount code: LRN15 and study specialized LV/MV/HV technical articles and studies.

Home / Technical Articles / Why and how much for fire protection of power plant?
Black smoke billows from an electrical fire at the power plant
Black smoke billows from an electrical fire at the power plant

Fire protection measures can be subdivided into life-safety and investment categories.


Life-Safety Measures

Life-safety measures are considered to be mandatory by  fire codes, building codes, or safety codes. As such, the codes mandate specific types of substation fire protection, with very little flexibility in their selection.


Investment Considerations

Investment-related  fire protection is provided to protect assets, conserve revenue, and help maintain service to customers. This type of fire protection is not commonly mandated by legislation but is driven by economic reasons such as asset losses, revenue losses, and the possible loss of customers.

Therefore, there is considerable  flexibility in the  fire risks that are mitigated, the  fire protection measures used, whether the risk is offset by purchasing insurance, or whether the risk of a loss is absorbed as a cost of doing business.

The selection of investment-related  fire protection can be done based on company policies and standards, insurance engineering recommendations, industry practices, specific codes and standards (IEEE 977 and NFPA 850), or by risk-based economic analysis.

TABLE 1 – Probability of Fire for Various Transformer Voltages

Transformer VoltageAnnual Fire Frequency
69 kV0.00034 fires/year
115–180 kV0.00025 fires/year
230–350 kV0.0006 fires/year
500 kV0.0009 fires/year

Source: IEEE 979, Guide for Substation Fire Protection.

The risk-based economic analysis is the evaluation of the investment measures in relation to the probability of  fire, the potential losses due to  fire, and the cost of the  fire protection measures.

This analysis requires a reasonable database of the probability of fires for the different hazard areas or types, an assessment of the effectiveness of the proposed fire protection measures, an estimate of the  fire loss costs, and a fair degree of engineering judgment. The potential losses usually include the equipment loss as well as an assessment of the lost revenue due to the outage resulting from the loss of equipment.

One of the most common risk-based economic analysis types is a benefit/cost analysis. This analysis is calculated using the following equation:

Power plant fire protection - Economic analysis

Normally, this ratio should be greater than one and preferably greater than two. A benefit/cost ratio of two means that the benefit (avoided  fire loss costs) is twice the cost of the  fire protection. Therefore it is a good investment.

One of the greatest difficulties is to estimate the frequency of  fire for the specific hazards. Some companies have extensive fire loss histories and loss databases. These databases can be used to estimate specific fire frequencies, but the results may be poor due to the small statistical sample size based on the company’s records. There are a number of other databases and reports that are in the public domain that provide useful data (i.e., NFPA data shop, EPRI Fire Induced Vulnerability Evaluation Methodology, and IEEE 979 Transformer Fire Survey). Table 1 shows the estimated probability of fire from the IEEE 979 Transformer Fire Survey.

Once the potential financial loss due to a fire has been calculated, the designer should input costs and effectiveness of any proposed  fire protection measure into the benefit/cost equation and determine the B/C ratio. If the B/C ratio is less than one, provision of the fire protection measure is not an acceptable investment.


Example of a Risk-Based Economic Analysis

The following is a simplified example of an analysis:

  • A substation has four 138-kV single-phase oil-insulated transformers. One of these transformers is a spare and is located remote from the others. The load supplied by these transformers is 25 MW. A water-spray deluge system is being considered to suppress or control a  fire in the trans-formers. The deluge system is expected to protect the adjacent transformers, but not save the transformer that catches  fire.

    The estimated cost of a deluge system for all three transformers is $60,000. The individual transformers have a replacement value of $300,000.
  • The utility’s chief financial officer questions whether this is a good investment.
  • The company uses a discount rate of 10% and requires that all investments have a benefit/cost ratio greater than two. The assigned value of energy is $25/MW. The standard amortization period is 25 years.
  • The annual frequency of  fire for a single 138-kV transformer is estimated as 0.00025  fires/year. Therefore, the combined frequency for the three transformers is 0.00075 fires/year.
  • The estimated effectiveness of the deluge system protecting the adjacent transformers is 0.9. The deluge system will not save the transformer in which the fire originates; it is assumed to be a total loss.
  • The  fire is assumed to originate in the center transformer in the bank of three single-phase transformers. It is assumed that in the absence of suppression, the fire will spread to destroy the two adjacent transformers. The spare transformer is not affected because it is remote from the other transformers.
  • The estimated station outage period for this scenario is the difference between the outage time to replace all three transformers (a fire in the center transformer could destroy all three transformers) and the outage time to replace the center transformer (assuming the deluge system will protect the adjacent transformers).

The outage time to replace a single unit is  five days and to replace three units is 40 days. Therefore, the expected outage loss period is 35 days.

The expected lost revenue is 35 days × 24 h/day × 25 MW/h × $25/MW = $525,000.

The estimated annual revenue and equipment loss costs = (composite annual  fire frequency)  ×
(revenue loss for the station outage period + replacement value of the adjacent transformers) =
(0.00075 fires/year) × [$525,000 + (2 × $300,000)] = $843.75/year.

The net present value of the annual revenue and equipment losses for the 25-year amortization period at a discount rate of 10% = $7659.

The benefit/cost ratio = $7659/[$60,000 × (1.0/0.9)] = 0.115.

Example conclusion //

The calculated benefit/cost ratio of 0.115 is considerably less than the min-imum required ratio of two. The proposal to install deluge protection should be rejected, since it is not economical. Other  fire protection measures could be considered, or the risk could be transferred by purchasing insurance to cover the possible loss of the assets (transformers) and the revenue. These other measures can also be analyzed using this methodology for economic risk analysis.

It should be noted that the above example does not include societal costs, loss of reputation, and possible litigation.

SOURCE // Substation Fire Protection – Don Delcourt, BC Hydro

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical engineering guides, research studies and much more! It helps you to shape up your technical skills in your everyday life as an electrical engineer.
More Information
author-pic

Edvard Csanyi

Electrical engineer, programmer and founder of EEP. Highly specialized for design of LV/MV switchgears and LV high power busbar trunking (<6300A) in power substations, commercial buildings and industry facilities. Professional in AutoCAD programming.

7 Comments


  1. Than Dai
    Aug 10, 2013

    What is pressure test?


  2. aGZEUSa
    Dec 07, 2011

    Each environment with daily network environments required strong energy-network system is very much needed protective measures. Given the human life,,, This is the recommended professional trained in specific electrical capacity of organized business plan, Agim-

Leave a Comment

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

  −  three  =  one

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

Subscribe to Weekly Newsletter

Subscribe to our Weekly Digest newsletter and receive free updates on new technical articles, video courses and guides (PDF).
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge