Done on the HV winding

On-load tap changers (or circuit tap changers), as the name suggests, permit tap changing and hence voltage regulation with the transformer on-load.

4 Essential Features of Transformer On-Load Tap Changer
4 Essential Features of Transformer On-Load Tap Changer (photo credit: on-electricity.blogspot.fr)

Tap changing is usually done on the HV winding for two reasons:

  1. Because the currents are lower, the tap changer contacts, leads, etc., can be smaller.
  2. As the HV winding is wound outside the LV winding, it is easier to get the tapping connections out to the tap changer.

Figure 1 below shows the connections for an on-load tap changer that operates on the HV winding of the transformer.

On-Load Tap Changer
Figure 1 – On-Load Tap Changer

The tap changer has four essential features:


1. Selector Switches

These switches select the physical tap position on the transformer winding and, because of their construction, cannot and must not make or break the load current.


2. Reactors

The load current must never be interrupted during a tap change.

Therefore, during each tap change, there is an interval where two voltage taps are spanned. Reactors (inductors) are used in the circuit to increase the impedance of the selector circuit and limit the amount of current circulating due to this voltage difference. Under normal load conditions, equal load current flows in both halves of the reactor windings and the fluxes balance out giving no resultant flux in the core.

With no flux, there is no inductance and, therefore, no voltagedrop due to inductance. There will be however, a very small voltage drop due to resistance.

During the tap change, the selector switches are selected to different taps (see Figure 2) and a circulating current will flow in the reactor circuit. This circulating current will create a flux and the resulting inductive reactance will limit the flow of circulating current.


3. Vacuum Switch

This device performs the duty of a circuit breaker that makes and breaks current during the tap changing sequence.


4. Bypass Switch

This switch operates during the tap changing sequence but, at no time, does it make or break load current, though it does make before break each connection.

An example of the tap changing sequence is detailed in Figure 2 (diagrams 1 through 10). Table 1 describes the sequence of operations for the tap changer of Figure 2 to change from tap 1 to tap 2. Changing to any other tap position is done similarly with the selector switch always moving sequentially (i.e., it is impossible to go from tap 1 to tap 3 directly, the order must be tap 1, tap 2, then tap 3).

The operating mechanism for the on-load tap changer is motor driven. Manual operation is used in the event of motor failure.

The sequence of operation is mechanically linked, orinterlocked, to ensure that all contacts always operate in their correct order. Any failure of the operating mechanism can result in severe damage to the transformers and tap changers.

Table 1 – Description of Tap Changing Sequence for Figure 1

No. Details of Tap-Changer operation
1Present position – tap changer selected to tap 1, bypass switch in, A + B, home position.
2Bypass switch selects lower circuit arm.
3Vacuum switch opens, removing load current from upper circuit arm freeing one half of selector switch for move.
4As there is no load current on upper arm of selector switch, it moves to tap 2.
5Vacuum switch closes – both selector switches onload, circulating current is limited by reactors.
6Bypass switch selects upper arm circuit arm. No arcing occurs as vacuum switch is closed and in parallel.
7Vacuum switch opens, removing load current from lower circuit arm, freeing lower selector switch for move.
8As there is no load current on lower arm of selector switch, it moves to tap 2.
9Vacuum switch closes – both selector switches onload, in parallel, on tap 2.
10With vacuum switch closed and selector switch on a single tap, the bypass switch can now return to its home position. Both reactor circuits stay normally in parallel. The tap change is now complete.
Illustration of an On-Load Change Operation
Figure 2 – Illustration of an On-Load Change Operation

The previous example describes one type of on-load tap changer. There are several other types inuse however, which may differ significantly from the type described.

Differences are usually in how the selection of taps is made and the degree of mechanization. However, most importantly, all on-load tap changers allow voltage changes to take place without interrupting the power circuit.

Function Principle of the OLTC (Video)

Cant see this video? Click here to watch it on Youtube.

Reference: Science and Reactor Fundamentals – Electrical CNSC Technical Training Group

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical engineering guides, research studies and much more! It helps you to shape up your technical skills in your everyday life as an electrical engineer.
More Information
author-pic

Edvard Csanyi

Electrical engineer, programmer and founder of EEP. Highly specialized for design of LV/MV switchgears and LV high power busbar trunking (<6300A) in power substations, commercial buildings and industry facilities. Professional in AutoCAD programming.

15 Comments


  1. Amey
    Jan 25, 2017

    What Precaution must be taken before Operating Tap Changer?


  2. Engr. Ghazanfar Ali Khan
    Sep 28, 2016

    What is the main difference between Diverter type and Selector type OLTCs?


    • Dave Summers
      Nov 27, 2017

      The diverter style is usually a high speed resistance switching style LTC that drops in place from the top of a transformer. Usally round. Only the diverter is removed for maintenance and the selector components share space with the transformer winding connections in the transformer.
      The selector style is usally welded compartment in front of transformer that uses a reactor and vacuum bottles for switching. All three phases are located in this oil compartment and its usually on the low side. These LTCs are usally located on the distribution side of the grid.


  3. Gordon N
    Feb 11, 2016

    A very one sided POV from an American engineer. The world mainly uses resistor type OLTC’s and have done so for 90 odd years. The largest producers of OLTC’s – Reinhausen and ABB offer some very good insight to operation of OLTC’s, but if you are an engineer involved with transformers and don’t understand these principles, maybe further training is needed rather than posting stupid questions on internet forums.


  4. C Gupta
    Oct 28, 2015

    I believe that USA still follows reactor type OLTC whereas rest of the world has changed over to high speed resistor type OLTC, Please add to the article above explaining these two technologies and their pros & cons (or success and failure rates).


  5. Gambhir singh
    Aug 14, 2015

    I want to know the full detail of online tape changer so pls tell about it


  6. James Jakubin
    Jul 22, 2015

    Thank you for this article on Tap Changer Operation. I am trying to understand this statement more clearly. “Reactors (inductors) are used in the circuit to increase the impedance of the selector circuit and limit the amount of current circulating due to this voltage difference”. I believe I understand how the fluxes cancel under normal load, but don’t understand how the voltage difference causes this impedance to increase?

    Can you clarify this or point me in the right direction please?


  7. Shivanand
    Jun 27, 2015

    How can find the tap value?


  8. Shivanand
    Jun 27, 2015

    What is the value of one tap in LOTC Transformer…..


    • Tisha Hayes
      Jul 21, 2015

      Often this is around 0.375% per step. There are usually 33 positions (16 above, one at and 16 below).


  9. An.kandasamy
    Apr 21, 2015

    OLTC function has been very clearly explained.Thanks to Edward


  10. Prodip Golder
    Mar 01, 2015

    I wanted to know load flow study of a power plant network with an example.


  11. Wilford Edwards
    Feb 07, 2015

    I wanted to know more about Electrical Engineering.


  12. Ramil
    Feb 04, 2015

    I would like to receive news regarding electrical engineering and more detailed calculations


  13. VIKAS JHA
    Jan 31, 2015

    Eep is an platform to know electrical engineering in a simple way

Leave a Reply to Engr. Ghazanfar Ali Khan

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

nine  ×  one  =  

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

Subscribe to Weekly Newsletter

Subscribe to our Weekly Digest newsletter and receive free updates on new technical articles, video courses and guides (PDF).
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge