Search

Premium Membership ♕

Save 50% on all EEP Academy courses with Enterprise Membership Plan and study specialized LV/MV/HV technical articles & guides.

Home / Technical Articles / Thumb rules, dos and don’ts in MV/HV switchgear testing and commissioning

System Commissioning

No matter the approach, it is necessary that the testing engineers who will be responsible for commissioning the switchgear have a solid comprehension of the equipment that will be utilized and the various modes of operation that will be utilized. It is also extremely important to ensure that both the employees and the plant are safe while commissioning, and the best way to do this is through careful planning as well as the recording of both procedures and safety measures.

Thumb rules, dos and don’ts in MV/HV switchgear testing and commissioning
Thumb rules, dos and don’ts in MV/HV switchgear testing and commissioning

Since there must not under any circumstances be a rush on the commissioning time, the planning for the project must take into consideration the possibility of delays occurring in the early stages of the project’s timeline.

Commissioning should also have a sufficient budget allocated to it. A common provision for commissioning is one percent to one and a half percent of the total cost of the electrical system.

This allowance will be more than offset by the higher reliability and decreased operating expenses that come from adequate commissioning.

Table of Contents:

  1. Standards Covering Switchgear Testing
  2. Switchgear Type Tests:
    1. Dielectric Measurements
    2. Temperature Rise Tests
    3. Circuit Breaker Making and Breaking Tests
      1. Terminal Faults
      2. Line Faults
      3. Capacitive Switching
      4. Out-Of-Phase Tests
      5. Short Time Currents
    4. Mechanical Endurance
    5. Switchgear Routine Tests
    6. On-Site Tests

1. Standards Covering Switchgear Testing

The following standards cover switchgear testing:

  • IEC 62271-100: High voltage switchgear and control gear – HV alternating current circuit breakers
  • IEC 62271-1: High-voltage switchgear and controlgear – Part 1: Common specifications for alternating current switchgear and
  • IEC 62271-101: High-voltage switchgear and controlgear – Part 101: Synthetic testing
  • IEC 62271-203: High voltage switchgear and control gear – Gas-insulated metal-enclosed switchgear for rated voltages of 72.5 kV and above
  • IEC 60060: High voltage test techniques
  • IEC 60480: Specifications for the re-use of sulphur hexafluoride (SF6) and its mixtures in electrical equipment
  •  controlgear

Go back to the Contents Table ↑


2. Switchgear Type tests

The following switchgear test are considered as type tests:

  1. Dielectric measurement.
  2. Temperature rise tests.
  3. Making and breaking tests.
  4. Mechanical endurance.

Let’s have a word about each test:


2.1 Dielectric Measurements

Is switchgear able to withstand the voltage stresses?

Dielectric measurements indicate that switchgear with a specific voltage rating can withstand the voltage stresses expected in service from switching operations or lightning surges. The switchgear is subjected to one-minute power frequency voltage withstand testing. A voltage greater than the rated voltage of the switchgear is used to validate proper clearances and insulation strength between phases, across open contacts, and between phase and earth.

The tests also examine the withstand capabilities of switchgear closing and opening resistors, GIS designs, and grading capacitors. When calculating the test voltage to be used, a suitable margin between the withstand voltage levels and transitory overvoltages that may occur during switching operations must be provided for.

Furthermore, the performance of asymmetric electrode morphologies at various high test voltage polarities must be examined.

However, additional elements, like humidity, dust, radiation, and especially the electrode design, can have a much larger impact on the breakdown strength of air than just pressure and temperature. Therefore, type test voltages employed in the lab require correction factors to adequately represent a range of real-world situations.

Switchgear operating at high altitude, where the air density is lower, requires, for instance, larger switchgear clearances to be accounted for in designs. To account for the higher withstand voltage of air at sea level, the type test voltage is also raised.

Type testing should be carried out under the most unfavorable conditions, as the dielectric strength of SF6 fluctuates with density.

Figure 1 – Dielectric tests performed on GIS switchgear

Dielectric tests performed on GIS switchgear
Figure 1 – Dielectric tests performed on GIS switchgear (photo credit: High Voltage Testing and Engineering Commission)

Tests on outdoor gear can be carried out in either dry or wet environments, depending on the requirements of the product. As a technique of ensuring suitable insulator profiles and creepage distances, the wet conditions make an attempt to take into account the effects of water cascading down the switchgear porcelain insulators. This is done by taking into account the wet circumstances.

The performance of insulators in dirty or low-temperature ice circumstances also needs to be evaluated and is the subject of particular agreements between the client or his engineer and the switchgear or insulator makers.

The purpose of the impulse resist tests is to demonstrate that the switchgear is able to endure surges that are caused by lightning as well as switching situations. These tests use waveforms that are going in both positive and negative directions. In most cases, switching surges are only applicable to equipment that was intended for rated voltages more than 300 kV and that falls into the insulating Range II category. The overall switchgear dimensions for this insulation category are mostly controlled by the requisite switching and lightning surge clearances.

A standard test consists of applying test voltages between each phase and earth in turn 15 times while the circuit breaker is closed and the remaining phases are earthed. Normally, a standard 1.2/50 s impulse voltage wave shape is used to simulate lightning strike conditions, and a 250/2500 s wave shape is used to simulate switching surges.

Additionally, test voltages are provided across each set of open circuit breaker contacts. This is done in addition to the previous step. If there are not more than two flashovers during any one series of 15 tests, then the overall test is regarded to have been successful. However, these discharges can only take place in self-restoring insulation (such as air, oil, or SF6 gas), therefore this requirement must be met.

In most cases, an inability to recover from a test failure caused by a breakdown of solid insulation is the outcome of the breakdown.

In the event that it is necessary, more investigations to verify this could be carried out.

Figure 2 – High-Voltage Testing and Partial Discharge Measurements in GIS-Air Connection GIS Bushing

High-Voltage Testing and Partial Discharge Measurements in GIS-Air Connection GIS Bushing
Figure 2 – High-Voltage Testing and Partial Discharge Measurements in GIS-Air Connection GIS Bushing (photo credit: dexotechpower.com)

The above GIS Test Transformers typically either use oil or SF6 as their insulating medium. Oil transformers have significantly higher power outputs and tuning ranges, however they cannot be connected directly to the GIS bus and must utilize external  air connections. SF6 transformers with direct SF6 bus to the test object are the preferred method of connection for PD measurements.

When the switchgear is subjected to rated voltages higher than 300 kV, a bias test is carried out on it. The design of the circuit breaker is tested under the conditions of a lightning strike with the switchgear in the open position and the waveform peaks in the opposite polarity by applying a power frequency to one terminal of the circuit breaker and a lightning impulse to the other terminal. This is done so that the design can be validated under these conditions.

In most cases, partial discharge tests are not required to be performed as a component of a full circuit breaker assembly type examination. However, partial discharge testing is especially useful for switchgear systems that include components that have solid insulation.

Because persistent internal breakdown will eventually result in chemical and thermal damage as well as the failure of the insulation, it is imperative that the insulation be discharge free at the rated voltage. However, very low intensity discharges are unavoidable in practice, and minimum permissible values are established based on practical experience in order to ensure a long life for both the insulation and the switchgear.

The oscillograph traces might be used to make an effort at determining the voltage levels that were present at the beginning and end of the discharge. An examination of the traces enables a determination to be made as to whether the failure was caused by voids in the insulation, corona discharge, or some other factor.

During the testing of the power frequency overvoltage, another option is to determine the maximum discharge level, which is measured in picocoulombs.

Suggested Video – Voltage withstand test on a GIS 123 kV

Interference from electromagnetic fields can be caused by external discharges. Corona breakdown can be observed visually in a dimly lit laboratory, and the voltages at the moment of genesis and extinction can be measured. Radio noise levels that are the result of external discharges are measured in decibels (dB) above a reference level that is expressed in microvolts (μV).

According to IEC 62271, Table 1 outlines the lightning impulse and switching overvoltage levels that circuit breakers are rated for.

Table 1 – Circuit breaker rated lighting impulse & switching overvoltage levels (IEC 62271)

Circuit breaker rated lighting impulse and switching overvoltage levels to IEC 62271
Table 1 – Circuit breaker rated lighting impulse & switching overvoltage levels to IEC 62271

Note: Per unit maximum permissible switching overvoltage = peak value (kV peak) / {rated value (kV rms) × √2 /3}

Go back to the Contents Table ↑


2.2 Temperature Rise Tests

Can closed switchgear contacts handle higher temperature?

When the switchgear contacts are closed, the current that should be passing through them is the one that corresponds to the correct power frequency rating. In order to establish the continuous ultimate temperature rise at various temperature sensor positions on the switchgear, plots of temperature against time are recorded.

The many switchgear components each have their own unique set of standard permissible temperature rise limits.

Membership Upgrade Required

This content is not available in your premium membership plan. Please upgrade your plan in order to access this content. You can choose an annually based Basic, Pro, or Enterprise membership plan. Subscribe and enjoy studying specialized technical articles, online video courses, electrical engineering guides, and papers.

With EEP’s premium membership, you get additional essence that enhances your knowledge and experience in low- medium- and high-voltage engineering fields.

Did you know?Save 50% on all video courses by purchasing Enterprise plan.

Upgrade

Already a member? Log in here

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical engineering guides, research studies and much more! It helps you to shape up your technical skills in your everyday life as an electrical engineer.
More Information
author-pic

Edvard Canji

Electrical engineer, programmer and founder of EEP. Highly specialized for design of LV/MV switchgears and LV high power busbar trunking (<6300A) in power substations, commercial buildings and industry facilities. Professional in AutoCAD programming.

Leave a Comment

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

20  +    =  twenty seven

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

EEP Hand-Crafted Video Courses

Check more than a hundred hand-crafted video courses and learn from experienced engineers. Lifetime access included.
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge