Search

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical guides, studies and much more! Apply 20% OFF Code: EEP09PE
Home / Download Center / Electrical Engineering Books and Technical Guides / Alternative (renewable) energy guides / 60 MW grid tied solar power plant with 115 kV/34.5 kV substation

System Power Flow

A solar (PV) plant consisting of arrays will output power to a grid-tied power substation. The output of the plant is 60 MW. The solar power plant will produce DC current which is routed through a set of series/parallel conductors to an inverter.

60 MW grid tied solar power plant with an attached 115kV/34.5 kV substation
60 MW grid tied solar power plant with an attached 115kV/34.5 kV substation (photo source: EPR Magazine)

The inverter outputs three phase AC current to a step-up transformer.

The step-up transformer outputs to a collector in the substation component, in which flows to the collector arrangement, feeder arrangement and key protection component. Finally, it is fed to the grid at 115 kV.


Substation Component Design

The purpose of the substation is to collect all solar array power and feed into the grid after stepping up voltage to distribution level. This substation is based on an Arcadia design, modified for the project.

Power flow is bottom to top, 34.5 kV bus to 115 kV bus. It will consist of the following major drawings (single-line drawings).

  • Collector – Input from solar arrays’ transformer.
  • Feeder – Output from collector, input to 34.5 kV bus.
  • Key Protection – Circuit breakers, protection relays, capacitor bank, and step-up transformer. Outputs to grid at 115 kV.

The power flow block diagram in Figure 1 shows the input current flow from array skids. Array skids contain the inverter and step-up transformer. Power flow is bottom to top.

Substation Power Flow Block
Figure 1 – Substation Power Flow Block

Substation Component Functions

Primary Transformer – The primary transformer is an 85 MVA that steps up the feeder bus input of 34.5 kV to desired 115 kV

Current Transformer (CT) – Drops current to manageable level for relay, usually between 1 and 5 amps.

Circuit Breakers – A device in key protection that opens the feeder switch when relay detects an overcurrent condition.

Relays – Relays are monitoring devices used to detect ground fault currents and reduce saturation.

If there is an overcurrent fault they command the circuit breakers to open the circuit. Once current reverts to normal level, the relay will command the circuit breaker closed.

Capacitor Bank – The 9.0 MVAR capacitor bank stabilizes harmonics associated with threephase currents and helps maintain a power factor of 0.95. Component specifications were provided by utility and Black & Veatch.

Surge Arrestor – Surge Arrestors are devices that are used to maintain equipment protected from overvoltage transients caused by lightning strikes, or switching over voltages within the substation itself. In this project they are used to protect the four terminals going into each of the three feeder transmission lines.

Title: 60 MW grid tied solar power plant with an attached 115 kV /34.5 kV substation – Black & Veatch
Format: PDF
Size: 1.9 MB
Pages: 40
Download: Right here | Get Download Updates | Get Premium Membership
60 MW grid tied solar power plant with an attached 115kV/34.5 kV substation
60 MW grid tied solar power plant with an attached 115kV/34.5 kV substation

Premium Membership

Premium membership gives you an access to specialized technical articles and extra premium content (electrical guides and software).
More Information

3 Comments


  1. Miguel Ángel
    Aug 02, 2019

    When I generate from solar plant, can I energyze the PT from the secondary?, I mean without voltaje from the 130kV substation?


  2. Suryaprakasarao k.v.
    Mar 24, 2019

    1)In the single line diagram circuit breakers,P.T.s,L.As,Isolators,capacitor banks, auxilary transformer are not shown.
    2)Capacitors,I think, are required to correct the inductive KVAr of the load system.For 85 MVA load PTR,more than 9 MVAr is required.
    3)CTs and PTs are used both for metering and protection.


  3. Manuel António Raúl João
    Mar 22, 2019

    Boa coisa

Leave a Comment

Tell us what you're thinking... we care about your opinion!

Subscribe to Weekly Digest

Get email alert whenever we publish new electrical guides and articles.