400/220KV GIS substation GURGAON
This project is made to overcome the electricity crises and to meet the power demand of Gurgaon region at Haryana. It describes the 400kV GIS system of POWERGRID, Gurgaon substation.
As the Gurgaon region is upcoming with multi industrial, financial sectors, commercial and residential complexes, offices, clubs and an improved infrastructure, there is a huge demand of electricity in this region which cannot be met by the existing structure of power supply.
To meet the requirement a 400/220kV GIS project is set up which is in its completion stage.
This project is associated with Northern Region Strengthening Scheme-VI (NRSS-VI) as agreed during the 18th Standing committee meeting of Northern Regional Transmission Planning held on 6th June 2005.
Mainly three types of contract have been issued:
Off-Shore Equipment – Includes Circuit Breaker, Isolators, Earth Switch etc. contract given to HYOSUNG Corp. , Korea
On-Shore Supply – Includes lightning arrestor, CVT, Wave Trap, Cables, Transformer, C&R Panel. Under LOA the contract has been given to ABB, BHEL, BPL, GSW, etc.
On-Shore Services – Installation of all Equipment including testing, commissioning and
handover.
This project is fed by LILO of existing 400kV Ballabhgarh-Bhiwadi transmission line through double circuit. Major towers in this line used are multi circuit on which four circuits at a time can be used to deliver power. Due to the major commercial and residential hub in this region the cost of land is very high and keeping in view the future hike in land prices these multi circuit tower are installed.
The other two circuits in these multi circuit towers can be used by accommodating two circuits of 400/220kV GIS substation at Manesar.
This project is equipped with latest technology of GIS System, GIS stands for Gas Insulated Switchgear in which switchgear assemblies (CB, DS, ES, CT, PT etc.) are enclosed in a metal enclosed chamber which in filled with gas (SF6 gas) and the enclosure is earthed. The total land used in this project is 9.5 acres.
This project describes the 400kV GIS system of POWERGRID, Gurgaon substation. There is total no. of five bays in 400 kV systems and seven nos. of bays in 220kV systems.
In this substation double bus single Breaker scheme has been used. The metal enclosure is made of non-corrosive aluminium. Due to light weight of aluminium, costly foundations are no longer required
Title: | Specification For Erection, Testing and Commissioning Of 66/11 kV Grid Substation – BSES Rajdhani Power Limited |
Format: | |
Size: | 18.5 MB |
Pages: | 453 |
Download: | Here 🔗 (Get Premium Membership) | Video Courses | Download Updates |
Interested in 132 kV & 400kV Switchgear
I really want to have more on electrical energy
generation
hoo i am elect system engg sf 6 breaker service person