Search

Premium Membership ♕

Save 10% on Pro Membership Plan with coupon DEC10 and study specialized LV/MV/HV technical articles and papers.

Home / Download Center / Electrical Engineering Books and Technical Guides / Electricity generation, t&d guides / Real-time corrective control in active distribution networks

Active distribution network

Conventionally, the electrical energy has been mainly produced by large power plants, and shipped through the transmission and distribution grids to the end customers. However, the recent quest for reduction of greenhouse gas, use of sustainable energy sources and higher energy efficiency in the transmission grid, has led to the continuous growth of comparatively much smaller Dispersed Generation Units (DGUs) exploiting renewable sources of energy and connected to Distribution Networks (DNs).

Real-time corrective control in active distribution networks
Real-time corrective control in active distribution networks

On the other hand, the existing distribution grid was not designed nor equipped to host DGUs and to become an “active distribution network”. This proliferation of DGUs raises challenges in many aspects of Distribution System Operator (DSO) activities, ranging from long-term planning to real-time control.

From system operation viewpoint, this change is expected to create new technical problems, for instance over- or under-voltages (typically in rural networks due to the long distance from the main substation), or congestion problems (typically in urban networks serving many loads).


Test systems used in this work

All distribution networks are three-phase and are assumed to operate in balanced conditions. The topology of the distribution networks is also assumed unchanged.


32-bus system

The 32-bus test system is a 20-kV distribution network connected to the external grid through a 132/20 kV transformer with fixed tap position. The network one-line diagram is shown in Figure 1 while the branch parameters are given in Table A.1.

The network hosts three 4.5-MVA synchronous generators driven by hydro turbines and one 3.33-MVA Doubly Fed Induction Generator (DFIG) driven by wind turbine. It feeds 12 loads modelled as constant current for active power and constant impedance for reactive power, plus three equivalent induction motors.

All DGUs operate in reactive power control mode. This is achieved by a PI controller that regulates the reactive power output according to the set-point value requested by the centralized controller.

The following measurements are collected throughout the network: active and reactive power and voltage magnitude at the terminals of the four DGUs, active and reactive power flows in the HV/MV transformer as well as its terminal voltage on the MV side, and voltages at five load buses.

32-bus test system: Network topology and measurement allocation
Figure 1 – 32-bus test system: Network topology and measurement allocation

75-bus system

The 75-bus system is an 11-kV urban network. Its one-line diagram is presented in Figure 2, while the branch parameters are given in Table A.2. The network is connected to the external grid through a 33/11 kV transformer equipped with an LTC.

The data were taken from the United Kingdom Generic Distribution System repository which is a collection of models representative of UK distribution networks.

75-bus test system: Network topology and measurement allocation
Figure 2 – 75-bus test system: Network topology and measurement allocation

The system consists of eight short-distance underground feeders, all directly connected to the main transformer and serving 38 loads modelled as constant current for active power and constant impedance for reactive power, and 15 more loads represented by equivalent induction motors.

Moreover, it includes 22 DGUs which are either 3-MVA synchronous generators driven by hydro turbines with 2.55-MW nominal power, or DFIG driven by wind turbines. Each DFIG is a onemachine equivalent of two 1.5-MW wind turbines operating in parallel. The nominal capacity of each DFIG is 3.33 MVA.

The DGU models are identical to those of the 32-bus test system. The number of each type of DGUs has been varied in different case studies, and thus, it will be mentioned where results are presented. It is assumed that the 22 DGUs have their active power, reactive power and voltage magnitude measurements telemetered and gathered by the centralized controller. The voltage at the 11-kV end of the transformer and the corresponding active/reactive power flows are also measured.

As regards load buses, the measurement configuration is such that no load is at a distance larger than two buses from a voltage monitored bus, see Figure 2.


YLPIC system

The YLPIC test system is largely inspired of a Belgian MV distribution network located in Wallonia and operated by ORES. It has been used in several work packages of the GREDOR project (https://gredor.be). The objective was to examine the system behaviour over future years, when more renewable DGUs (wind and PV) would be installed.

To do so, a likely situation in 2030 has been considered with high penetration of renewable DGUs and new loads (mainly electrical vehicles and heat pumps).

The network is a 328-bus, 10-kV distribution grid connected through two transformers to the 70-kV transmission system. The latter is represented by a Thevenin equivalent and the transformers are equipped with Load Tap Changers (LTCs). The one-line diagram is shown in Figure 3.


Main substation

The main substation hosts two 70/10 kV transformers which are connected to two separate 10-kV busbars. The latter can be connected through a bus-coupler, if needed. Each transformer has a permanent rating of 20-MVA.

In normal operation, considered here, the bus-coupler is closed and only one transformer (referred to as main transformer hereafter) is in operation. When the power exchange between the MV grid and the transmission network is high (i.e. high consumption and low generation, or low consumption and high generation), both transformers are in operation and the bus-coupler is open (this is required since both transformers do not have exactly the same nominal secondary voltages).

Both transformers are equipped with LTCs. From past recordings it is known that the voltage on the transmission side can vary from 65-kV (0:93 pu) to 77-kV (1:10 pu), depending on the system operating conditions.

On the distribution side, however, voltages must be kept within a tighter interval.

328-bus YLPIC test system: Network topology and measurement allocation
Figure 3 – 328-bus YLPIC test system: Network topology and measurement allocation

Dispersed generation

Currently four wind-turbine units, with a total installed power of 20.5 MW, are connected to the MV buses. On the other hand, the existing PV installations as well as the Combined Heat and Power (CHP) units are all connected to the Low Voltage (LV) network.

Since setting up a communication infrastructure down to LV level does not seem realistic, DGUs connected to LV networks are not considered controllable. Instead, the focus is on DGUs connected to the MV grid.

Title:Real-time corrective control in active distribution networks by Hamid Soleimani Bidgoli (Submitted in partial fulfilment of the requirements for the degree of Doctor of Philosophy (Ph.D.) in Engineering Sciences at Academie universitaire Wallonie-Europe Universite de Liege)
Format:PDF
Size:11.1 MB
Pages:189
Download:Right here | Video Courses | Membership | Download Updates
Real-time corrective control in active distribution networks
Real-time corrective control in active distribution networks

Premium Membership

Get access to premium HV/MV/LV technical articles, advanced electrical engineering guides, papers, and much more! It will help you to shape up your technical skills in your everyday life as an electrical engineer.
50% Discount 💥 - Save 50% on all 90+ video courses with Enterprise Membership plan.

More Information

4 Comments


  1. Engr Moses Ajayi
    Aug 23, 2021

    The aticle is very technical and useful for engineers desirous to become consultants specially in Power system design and analysis.


  2. Mohamed Omar Morad
    May 01, 2020

    This is a very good article


  3. ramkumar kaliyamoorthy
    Apr 30, 2020

    need more technical online data


  4. Joel John Lugia Lawiya
    Apr 30, 2020

    More information about the transformer all

Leave a Comment

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

  −  4  =  five

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

EEP Hand-Crafted Video Courses

Check more than a hundred hand-crafted video courses and learn from experienced engineers. Lifetime access included.
Experience matters. Premium membership gives you an opportunity to study specialized technical articles, online video courses, electrical engineering guides, and papers written by experienced electrical engineers.