Search

Premium Membership ♕

Learn from experienced engineers and study specialized technical articles, studies & courses. Save 50% on courses with the Enterprise Plan.

Home / Download Center / Electrical Engineering Books and Technical Guides / Electricity generation, t&d guides / Construction of a grid substation for engineers and technical supervisors

Busbar schemes

The commonly used busbar schemes at substations are single busbar, main and auxiliary busbar, double busbar, double main and auxiliary busbar and one and a half breaker scheme.

Construction of a grid substation for engineers and technical supervisors
Construction of a grid substation for engineers and technical supervisors

Single busbar arrangement

This is the simplest switching scheme in which each circuit is provided with one circuit breaker. This arrangement offers little security against busbar faults and no switching flexibility resulting into quite extensive outages of busbar and frequent maintenance of busbar isolator(s).

The entire substation is lost in case of a fault on the busbar or on any busbar isolator and also in case of maintenance of the busbar.

Another disadvantage of this switching scheme is that in case of maintenance of circuit breaker, the associated feeder has also to be shutdown.

Typical single busbar arrangement is shown in Figure 1.

Typical single busbar arrangement
Figure 1 – Typical single busbar arrangement

Main and auxiliary bus arrangement

This is technically a single busbar arrangement with an additional busbar called “Auxiliary bus” energized from main busbars through a bus coupler circuit, i.e., for ‘n’ number of circuits, it employs ‘n + 1’ circuit breakers.

Each circuit is connected to the main busbar through a circuit breaker with isolators on both sides and can be connected to the auxiliary busbar through an isolator.

The additional provision of bus coupler circuit (Auxiliary bus) facilitates taking out one circuit breaker at a time for routine overhaul and maintenance without de-energizing the circuit controlled by that breaker as that circuit then gets energized through bus coupler breaker.

As in the case of single bus arrangement, this scheme also suffers from the disadvantages that in the event of a fault on the main busbar or the associated isolator, the entire substation is lost. This bus arrangement has been extensively used in 132 kV substations.

Typical main and auxiliary busbar arrangement is shown in Figure 2.

Typical main and auxiliary busbar arrangement
Figure 2 – Typical main and auxiliary busbar arrangement

One and a half breaker arrangement

In this scheme, three circuit breakers are used for controlling two circuits which are connected between two busbars. Normally, both the busbars are in service.

A fault on any one of the busbars is cleared by opening of the associated circuit breakers connected to the faulty busbar without affecting continuity of supply. Similarly, any circuit breaker can be taken out for maintenance without causing interruption.

Typical one and a half breaker arrangement is shown in Figure 3.

Typical one and a half breaker arrangement
Figure 3 – Typical one and a half breaker arrangement

Load transfer is achieved through the breakers and, therefore, the operation is simple. However, protective relaying is somewhat more involved as the central (tie) breaker has to be responsive to troubles on either feeder in the correct sequence.

Besides, each element of the bay has to be rated for carrying the currents of two feeders to meet the requirement of various switching operations which increases the cost.

The breaker and a half scheme is best for those substations which handle large quantities of power and where the orientation of out going feeders is in opposite directions. This scheme has been used in the 400 kV substations.

Title:Construction of a grid substation for engineers and technical supervisors – RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LTD.
Format:PDF
Size:4.70 MB
Pages:150
Download:Right here | Video Courses | Membership | Download Updates
Construction of a grid substation for engineers and technical supervisors
Construction of a grid substation for engineers and technical supervisors

Premium Membership

Get access to premium HV/MV/LV technical articles, advanced electrical engineering guides, papers, and much more! It will help you to shape up your technical skills in your everyday life as an electrical engineer.
50% Discount đŸ’„ - Save 50% on all 90+ video courses with Enterprise Membership plan.

More Information

2 Comments


  1. Joseph Onimisi Ondeku
    Apr 27, 2022

    Very impressive work


  2. Mahmud
    Mar 01, 2021

    I want to know about simulation of an Escalator using Embedded system

Leave a Comment

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

seventy two  ⁄  8  =  

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

Subscribe to Weekly Newsletter

Subscribe to our Weekly Digest newsletter and receive free updates on new technical articles, video courses and guides (PDF).
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge