11/0.43 kV distribution substation

The decision of a MV or LV supply will depend on local circumstances and considerations such as those mentioned above, and will generally be imposed by the utility. When a decision to supply power at MV has been made, there are two widely-followed methods of proceeding.

Installation and commissioning of 11/0.43 kV substation
Installation and commissioning of 11/0.43 kV substation

These methods are:

The first method of proceeding is that the power-supplier constructs a standard substation close to the consumer’s premises, but the MV/LV transformer is located in transformer chamber inside the premises, close to the load center.

Second one points the consumer to constructs and equips his own substation on his own premises, to which the power supplier makes the MV connection.

This paper discusses about installation of 11/0.44 kV substation. It also includes the designing of the double pole structure. It includes the study of various equipment which are installed on dipole structure.

Site selection of substation

The consumer must provide certain data to the utility at the earliest stage of the project. (maximum anticipated power demand (KVA), layout plans and elevations showing location of proposed substation, degree of supply continuity required from the information provided by the consumer), the power-supplier must indicate:

  1. The type of power supply proposed, and define the kind of power-supply system: over headline or underground-cable network, the service connection details: single line service, ring-main installation, or parallel feeders, and the power (kVA) limit and fault current.
  2. The nominal voltage and rated voltage (Highest Voltage for equipment)

Metering details which define: The cost of connection to the power network and tariff details (consumption and standing charges).

11/0.43 kV substation construction drawing
11/0.43 kV substation construction drawing

Construction

Before any installation work is started, the official agreement of the power supplier must be obtained. The request for approval must include the following information, largely based on the preliminary exchanges noted above:

  1. Location of the proposed substation;
  2. Single-line diagram of power circuits and connections, together with earthing circuit proposals;
  3. Full details of electrical equipment to be installed, including performance characteristics;
  4. Layout of equipment and provision for metering components;
  5. Arrangements for power factor improvement if required. Arrangements provided for emergency standby power plant (MV or LV) if eventually required.

Commissioning of 11/0.433 kV substation

After testing and checking of the installation by an independent test authority, a certificate is granted which permits the substation to be put into service. When required by the authority, commissioning tests must be successfully completed before authority is given to energize the installation from the power supply system.

Even if no test is required by the authority it is better to do the following verification tests: measurement of earth-electrode resistances, continuity of all equipotential earth-and safety bonding, conductors, inspection and functional testing of all MV components, etc.

Title:Installation and commissioning of 11/0.43 kV substation – Ajinkya Lonare, Pravin Bodadkar, Shuchiket Darunde, Dr. G.H. Agrawal at Department Of Electrical Engineering, KDK College of Engineering, Nagpur, Maharashtra, India
Format:PDF
Size:625.7 KB
Pages:6
Download:Right here | Video Courses | Membership | Download Updates
Installation and commissioning of 11/0.43 kV substation
Installation and commissioning of 11/0.43 kV substation

Premium Membership

Get access to premium HV/MV/LV technical articles, advanced electrical engineering guides, papers, and much more! It will help you to shape up your technical skills in your everyday life as an electrical engineer.
50% Discount 💥 - Save 50% on all 90+ video courses with Enterprise Membership plan.

More Information

7 Comments


  1. Maturi Sudhakar
    Oct 26, 2023

    If there is any vacancy in this project?
    Please send me the details..
    Thank you


  2. SUBRATAKUMAR BERA
    Feb 24, 2023

    Good. Earthing of switch yard substation shaLL BE COVERED.


  3. FIROZ AHMED
    Oct 05, 2022

    Sir, I want to front view diagram of 11/0.433 kv,160 kva transformer pole mounted with ct pt installation


  4. Bikash Rout
    Sep 30, 2021

    I want to download this PDF (11kv/440v distribution substation)


  5. sai prasad reddy
    Jan 10, 2020

    It was better


  6. shaik ithihas
    Jan 10, 2020

    simple transmission MV/LV


  7. Abhishek
    Jan 09, 2020

    Dear sir…is full pdf available for the above 11kv/440v book by ajinkya lonare…?

Leave a Reply to SUBRATAKUMAR BERA

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

22  ⁄  twenty two  =  

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

Subscribe to Weekly Newsletter

Subscribe to our Weekly Digest newsletter and receive free updates on new technical articles, video courses and guides (PDF).
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge