Search

Premium Membership ♕

Limited Time Offer: Save 15% on PRO Plan with discount code: LRN15 and study specialized LV/MV/HV technical articles and studies.

Home / Download Center / Electrical Engineering Books and Technical Guides / Power substation guides / Design process for the new primary substation (structure selection and calculations)

Primary substation

The scope of this document is to study and develop methodology by which techno/economical dimensioning of primary substation in power system can be done. The document considers existing power supply system and changes that should be done in the process of designing of new substation.

Designing process of the new primary substation (structure selection and calculations)
Designing process of the new primary substation (structure selection and calculations)

The equipment that will be used in the substation is described. All necessary calculations are made, on the basis of which the equipment is selected according to state standards.


Objectives

Designing of a substation is a process, when you have to consider not only technical aspects of the issue, but economical aspects as well. This work considers the special features and parameters of power system that could finally affect a power substation.

The work address the following issues:

  • Definition of optimal structure of power substation according to the investment cost, operational cost and reliability cost, in long run;
  • Estimating techno-economic range of power substation structure depending on the total peak load of the area;
  • Evaluating the effect of outage costs in techno-economic studies.
The second chapter of the work is focused on the techno-economic planning of electricity networks. The main principles of techno-economic planning are mentioned, and introduction into the life-time cost analyses is presented. Chapter three introduces primary substation planning process. Also the role of primary substation in the power system is described.

The fourth chapter considers a technical view on primary substation. The main components of primary substation are mentioned and described.

In chapter five the case studies about substation design are presented. Methodology, which was already described, is adapted to the chosen region. Chapter six includes final conclusion.


Main transformers

The function of main transformers on primary substation is to step-down incoming voltage to a suitable level. Power transformers make the biggest contribution to the total cost and represent to of the total substation cost.

The amount of main transformers is selected according to each case-area features, but, in general, it is installed from one to six transformers on primary substations to convert incoming power.

The sum of all transformers capacities is equal to a substation’s capacity.

Sngle busbar system with three transformers
Figue 1 – Single busbar system with three transformers

Types and number of main transformers

The most common main transformers, which are used in usual regional and MV networks, are three-phase main transformers. The main reason is that the use of one three-phase transformer on primary substation instead of using three single-phase transformer units is more beneficial. One three-phase transformer needs less empty space, has lower losses and lower maintenance cost than three single-phase transformers of equivalent capacity.

The type of transformer on primary substation is selected according to its application and case-area features.

Sometimes when the load growth is expected in the future, some transformers might be installed without special additional cooling equipment (such as fans). If the load peak creates the need, it will be possible to add such equipment and to boost the capacity of transformer.

There are a lot of special types of transformers, which are used to accommodate special requirements. For instance, for distribution applications it is often required to convert power to two voltage ranges. In this case three-winding transformers are used to provide three voltage levels for some substations and few loads nearby.

Figure 2 shows a primary substation with three-winding transformer.

Substation with three-winding transformer
Figure 2 – Substation with three-winding transformer

One more very important special transformers type is low footprint transformer. It is used to be fit into substations, which were originally designed for smaller units.

Another category is high impedance transformers, which are designed to limit fault currents. These transformers have a higher cost, but reduce fault currents and breaker requirements to appropriate levels.

The majority of primary substation main transformers are delta-connected on the high side and either wye-connected on the low side. If power transformer has a big capacity, wye-connection is utilized in order to decrease linear currents on the low side. The same rules are also used for three-winding transformers.

The majority of three-winding transformers also have delta-connection scheme on the high voltage side. If it is needed to decrease linear current on medium-voltage or low-voltage side, wye-connection might be used.

As it was mentioned, primary substations vary by the amount of transformers. Each variation has advantages and disadvantages. For instance, a substation with a single transformer will be unable to provide a supply, if this transformer fails. A substation with two or more transformers could still function in case of a failure of any transformer. Thus, the loading on remaining transformers could be increased, and they could operate for few hours before overheating.

Moreover, main transformers of big capacity (over 60 MVA) are costly and difficult to transport. Because of that, there are some economic reasons for using two or three transformers of smaller capacity instead of using a single transformer of greater capacity.

It should be noted that the forecasted load growth is not always accurate enough, and there might be a need in increasing transformers capacity.

But, it is not easy to carry out for all types of substations. For example, the capacity of main transformers on primary substation, which is originally planned for multiple transformers, could be increased in stages by paralleling of additional transformer without serious reconstruction of primary substation.

The reconstruction of a single transformer substation will take more time and investments.

Title:Designing process of a new primary substation (structure selection and calculations) – Semen Lukianov at LAPPEENRANTA UNIVERSITY OF TECHNOLOGY, School of Energy Systems, Electrical Engineering
Format:PDF
Size:2.3 MB
Pages:95
Download:Here 🔗 (Get Premium Membership) | Video Courses | Download Updates
Designing process of the new primary substation (structure selection and calculations)
Designing process of the new primary substation (structure selection and calculations)

Premium Membership

Get access to premium HV/MV/LV technical articles, advanced electrical engineering guides, papers, and much more! It will help you to shape up your technical skills in your everyday life as an electrical engineer.
50% Discount 💥 - Save 50% on all 90+ video courses with Enterprise Membership plan.

More Information

3 Comments


  1. Blessing I.O
    Mar 29, 2023

    i would like to subscribe.


  2. hariom sharma
    Mar 29, 2023

    The design of substations depends on variety of factors.Power requirement and voltage variation permitted by supply authorities and stability calculations particularly in case of traction substations where load in fluctuating and only two phases are used on high voltage side of traction transformer causing unbalance in power supply system need careful consideration.


  3. Pedro ceferino Antonio seguel
    Jan 18, 2021

    Buen día… Soy oficial especializado en electricidad e instrumentación

Leave a Comment

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

fifty six  ⁄    =  8

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

Subscribe to Weekly Newsletter

Subscribe to our Weekly Digest newsletter and receive free updates on new technical articles, video courses and guides (PDF).
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge