132/33/11 kV Kawasoti substation
Under the Project, a new 132/33/11 kV Kawasoti substation will be constructed with a transformer of 132/33 kV, 30 MVA. The new substation will receive power from a higher capacity 132 kV transmission line with greater reliability than the existing 33 kV sub-transmission line.
The 132 kV transmission line will be connected to the 33 kV transmission line system through the transformer to reinforce the 33 kV transmission line. As the result, there will be a drastic reduction in the voltage drops, power outages, and transmission line loss.
The exponential growth of power demand in the Kawasoti area has risen as a result of the industrial and commercial development caused by the diverse influx of settlers over a period of 5 years up to 2004.
But the installed capacities of the existing 33 kV and 11 kV facilities are not sufficient for the actual power demand.
The 33 kV sub-transmission line in this area has an excessive voltage drop beyond the value of 5% specified in the regulations for the country.
There are frequently accidental blackouts on the 33 kV sub-transmission lines and the 11 kV distribution lines and the power supply has therefore become unstable. The transformer capacities of the existing substations will soon be below the required capacity.
The purpose of the project to improve the electrical supply system is to enhance and continue the improvement of living standards of the residents of the Kawasoti area and to reduce poverty and minimize the difference in living standards between cities and rural areas, which are being hindered by the poor electrical system.
Design Policy
er supply in response to the rapidly increasing population by solid growth of commerce and industry. For the design of electrical equipment for the realization of stable power supply, the present situation of Kawasoti area, where economic growth is highly expected as one of the largest settlement areas in Nepal, shall be considered.
The long term sustainability of the project and maximum benefit from the implementation of the project is aimed at by keeping the cost to a reasonable level.
The site of the new substation is to be adjacent the 132kV transmission line power source and transmission line work will be minimized. The substation is to be constructed at the load center so that the decreasing voltage drop and transmission losses can be realized efficiently.
Involuntary removal of inhabitants and public facilities shall be avoided as much as possible.
Transformer capacity will be determined so as to cover electricity demand for at least 10 years after 2005.
he confirmation of transformer capacity, which is the main equipment to be supplied by the Project, shall be made after sufficient analysis and study of recent trends in electricity demand of Kawasoti Substation and the demand forecast made by Nepal Electricity Authority (NEA).
Title: | Design study for construction of new substation in Kingdom of Nepal – Japan International Cooperation Agency |
Format: | |
Size: | 2.60 MB |
Pages: | 59 |
Download: | Here 🔗 (Get Premium Membership) | Video Courses | Download Updates |
Recommended Reading – Dos and don’ts in site testing and commissioning distribution and transmission plants
Dos and don’ts in site testing and commissioning distribution and transmission plants
50 MEGAWATT POWER PLANT WILL DEVELOP IN BD BY 2020 DEC.EXP/COST ADVICE
All the PDF articles are very useful to me and thanks a lot for that
It is a very useful material for student as well as professional electrical engineers,I wish ,this should hav e been there when I graduated .I am old time graduate passed in 1973 and in those days we have to struggle to get information and knowledge.
I am very happy that I have subscribed fior this site.Mr.Csanyi is so regularly and diligently distributing knlowledge in Electrical engineering .Thank you Sir!