SCADA, RTUs and PLCs

Most of digital control systems use a Supervisory Control And Data Acquisition (SCADA) with Remote Terminal Unit (RTU) for monitoring the metering devices for incoming and outgoing feeders.

Implementation Of SCADA System For Controlling And Monitoring 132/33/11 kV Substation
Implementation Of SCADA System For Controlling And Monitoring 132/33/11 kV Substation (photo credit: alamirgroupinc.com)

Beside SCADA and RTUs digital control systems use a Programmable Logic Control (PLC) technique for controlling and monitoring the system inside substations by professional engineers.

A practical monitoring system of SCADA with RTU has been introduced in this paper for Falluja substation. There are 3 devices of RTUs are used to collect data from ION 6200 devices installed inside incoming and outgoing panels for low Voltage (LV 380V), 33KV and 11KV.

Then the data from each RTU will be send to the SCADA (main Computer) via special router, the SCADA system used ION enterprise software supplied by AREVA company in addition to all panels which supplied by the same company.

Many difficulties were appeared during the work, such as mistakes of IPs, setting parameters, selection of protocols, and matching of devices have solved until the normal work was obtained to the substation.


How it works?

SCADA systems are used to monitor and control a plant or equipment in industries such as telecommunications, water and waste control, energy, oil and gas refining and transportation.

These systems encompass the transfer of data between a SCADA central host computer and a number of Remote Terminal Units (RTUs) and/or Programmable Logic Controllers (PLCs), and the central host and the operator terminals.

The physical ION Enterprise Network Configurations of Falluja Substation
The physical ION Enterprise Network Configurations of Falluja Substation

A SCADA system gathers information (such as where a leak on a pipeline has occurred), transfers the information back to a central site, then alerts the home station that a leak has occurred, carrying out necessary analysis and control, such as determining if the leak is critical, and displaying the information in a logical and organized fashion.

These systems can be relatively simple, such as one that monitors environmental conditions of a small office building, or very complex, such as a system that monitors all the activity in a nuclear power plant or the activity of a municipal water system.

Traditionally, SCADA systems have made use of the Public Switched Network (PSN) for monitoring purposes. Today many systems are monitored using the infrastructure of the corporate Local Area Network (LAN)/Wide Area Network (WAN).

Title:Practical Implementation of SCADA System for Falluja Substation – Dr. Salih Mohammed Salih, IEEE Member
Format:PDF
Size:2.1 MB
Pages:19
Download:Right here | Video Courses | Membership | Download Updates
Implementation Of SCADA System For Controlling And Monitoring 132/33/11 kV Substation
Implementation Of SCADA System For Controlling And Monitoring 132/33/11 kV Substation

Premium Membership

Get access to premium HV/MV/LV technical articles, advanced electrical engineering guides, papers, and much more! It will help you to shape up your technical skills in your everyday life as an electrical engineer.
50% Discount 💥 - Save 50% on all 90+ video courses with Enterprise Membership plan.

More Information

8 Comments


  1. RANVEER VERMA
    Jun 22, 2021

    I hope you are doing well, can you send me latest updates for SCADA, PLC, DCS and Industrial Automation.


  2. edwin Iraola
    Apr 28, 2021

    I want to ask about connections of SCADA & RTU monitoring ,
    is this necessary Motorized breaker is only applicable to SCADA and RTU.

    Since our PSS main breaker is not Motorized what is our options to utilized SCADA & RTU monitoring system

    your reply is very helpfull

    Regards

    Edwin Iraoal


  3. Ali Akbar
    Mar 04, 2021

    Can you send SCADA Substation installation testing & commissioning procedures


  4. Tarun Pathak
    Aug 18, 2020

    I am electrical engineering graduate and find a job in core so please help me to find the job


  5. solomon abera
    Aug 16, 2019

    pleas,explain clearly about the operation of per phase transformer


  6. Yann saidi
    Aug 15, 2019

    Tres intéressé par vos note de l’electrotechnique


  7. SHAIKH ZAFRUDDIN
    Aug 15, 2019

    Iam Graduate Electrical Engineer with MBA and 15 year experience in execution of Transmission and Distribution and solar. Now I’m working as a sr.manager in Tractebel engineering pvt ltd as power and ICT ducts utility expert.


  8. Ibrahim Mohammad Tarawneh
    Dec 07, 2018

    Dear Sir,

    I hope you are doing well, can you send me last update for SCADA, PLC and DCS.

Leave a Reply to Yann saidi

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

eight  ×    =  eight

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

Subscribe to Weekly Newsletter

Subscribe to our Weekly Digest newsletter and receive free updates on new technical articles, video courses and guides (PDF).
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge