Search

Premium Membership ♕

Save 50% on all EEP Academy courses with Enterprise Membership Plan and study specialized LV/MV/HV technical articles & guides.

Home / Technical Articles / How to: Isolation, maintenance, and restoration of a 132kV GIS Transformer Bay and Line Bay

Operating 132kV GIS Transformer Bay & Line Bay

This article aims to provide a comprehensive guide to the standard operating procedures (SOPs) for the isolation, maintenance, and restoration of a 132kV GIS Transformer Bay and Line Bay. It will delve into detailed safety checks, specific steps to be followed during the isolation process, and the restoration protocols to be adhered to post-maintenance.

How to: Isolation, maintenance, and restoration of a 132kV GIS Transformer Bay and Line Bay
How to: Isolation, maintenance, and restoration of a 132kV GIS Transformer Bay and Line Bay (on photo: Blackhill Substation, Scotland, credit: Kirby Group)

Additionally, the article will cover the procedures for handling transformer oil sampling, a critical aspect of maintaining transformer health and performance.

As yo already know, high Voltage (HV) substations are critical components of the electrical grid, playing a pivotal role in ensuring the reliability and stability of power transmission and distribution. Among these, the 132kV Gas Insulated Switchgear (GIS) substations are particularly significant due to their compact design, enhanced safety features, and superior operational efficiency.

The intricate nature of 132kV GIS substations necessitates stringent and precise operating procedures to ensure the safety of personnel, the longevity of equipment, and the uninterrupted delivery of electricity.

By systematically outlining these procedures, this article seeks to serve as a valuable resource for electrical engineers, maintenance personnel, and safety officers involved in the operation and upkeep of 132kV GIS substations.

The meticulous application of these SOPs not only enhances operational efficiency but also significantly mitigates the risks associated with high-voltage electrical systems.

Table of Contents:

  1. Standard Operating Procedure for Isolation and Maintenance of a 132kV GIS Transformer Bay:
    1. Isolation Procedure
    2. Checking for Live Parts
    3. Restoration Procedure
    4. Detailed Safety Checks
  2. SoP for 132kV Power Transformer Trip & Restoration:
    1. Objective
    2. Scope
    3. Circuit Breaker Trip Response:
      1. Differential Relay Operation
      2. Mechanical Protection Operation
      3. General Steps
    4. Conclusion
  3. SoP for 132kV Line Trip & Restoration:
    1. Objective
    2. Scope
    3. Elaboration on Procedures: (132KV Line Bay Operation):
      1. Line Circuit Breaker Trip Response
      2. Differential Relay Operation
      3. Distance Relay Operation
      4. General Steps
    4. Conclusion
  4. SOP for Transformer Oil Sampling:
    1. Objective
    2. Scope
    3. Procedure
    4. Oil Sampling in Aluminium Bottle
    5. Oil Sampling in Glass Bottle
    6. Bottle Samples for Screen Tests
    7. Syringe Samples for Dissolved Gas Analysis
  5. BONUS (PDF) 🔗 Download 132kV GIS Drawings of HV Devices and LCC + Design & Execution Guide (PDF)

1. Standard Operating Procedure For

Isolation and Maintenance of a 132kV GIS Transformer Bay

The primary aim of this procedure is to provide a comprehensive guide for the operation, isolation, and restoration of the 132kV transformer bay within a high-voltage (HV) substation.

This procedure outlines the specific steps required to isolate and restore the 132kV transformer bay, ensuring that all activities are conducted safely and effectively. Isolation is necessary for performing maintenance, repairs, or upgrades, and it involves de-energizing and securing the transformer bay to protect personnel and equipment.

Restoration involves re-energizing and bringing the transformer bay back into service following maintenance activities.

This procedure aims to minimize downtime, prevent accidents, and maintain the reliability and stability of the electrical supply.

Figure 1 – Single Line Diagram for the 132kV Transformer Bay at Substation

Single Line Diagram for the 132kV Transformer Bay at Substation
Figure 1 – Single Line Diagram for the 132kV Transformer Bay at Substation

Go back to Content Table ↑


1.1 Isolation Procedure

Step No.1 – Open the E02 Q0 Transformer Bay Circuit Breaker:

  1. Navigate to the control panel corresponding to the E02 Q0 Transformer Bay.
  2. Locate the circuit breaker control switch and set it to the “Open” position.
  3. Verify that the circuit breaker has successfully opened by checking the indicator lights on the control panel.

Step No.2 – Open the E02 Q1 Bus Isolator:

  1. Identify the E02 Q1 Bus Isolator, which disconnects the busbar from the transformer bay.
  2. Operate the control mechanism to move the isolator to the “Open” position.
  3. Confirm that the bus isolator is fully open, ensuring there is no physical connection between the busbar and the transformer.

Step No.3 – Open the E02 Q9 Line Isolator:

  1. Locate the E02 Q9 Line Isolator, which isolates the transmission line from the transformer bay.
  2. Actuate the isolator to the “Open” position using the control handle or switch.
  3. Check the status indicators to verify that the line isolator is completely open.

Step No.4 – Close the E02 Q51, E02 Q53, and E02 Q8 Earthing Switches:

  1. Identify the earthing switches E02 Q51, E02 Q53, and E02 Q8, which ground the disconnected equipment for safety.
  2. Operate each earthing switch to the “Close” position.
  3. Ensure that each earthing switch is securely closed, and that the equipment is properly earthed, providing a safe work environment for maintenance personnel.

Figure 2 – Isolation of 132kV GIS Transformer Bay

Isolation of 132kV GIS Transformer Bay
Figure 2 – Isolation of 132kV GIS Transformer Bay

Go back to Content Table ↑


1.2 Checking for Live Parts

Step No.1 – Verify De-energization with a Live Line Tester:

  1. Use a live line tester to check that no part of the MV bushing and busbar is live.
  2. Perform the test on the MV bushing first, ensuring no voltage is present.
  3. Repeat the test on the busbar, confirming complete de-energization.
  4. Record the test results and proceed only if both tests confirm that the equipment is de-energized.

Membership Upgrade Required

This content is not available in your premium membership plan. Please upgrade your plan in order to access this content. You can choose an annually based Basic, Pro, or Enterprise membership plan. Subscribe and enjoy studying specialized technical articles, online video courses, electrical engineering guides, and papers.

With EEP’s premium membership, you get additional essence that enhances your knowledge and experience in low- medium- and high-voltage engineering fields.

Did you know?Save 50% on all video courses by purchasing Enterprise plan.

Upgrade

Already a member? Log in here

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical engineering guides, research studies and much more! It helps you to shape up your technical skills in your everyday life as an electrical engineer.
More Information
author-pic

Muhammad Kashif

Muhammad Kashif Shamshad is an Electrical Engineer and has more than 17 years of experience in operation & maintenance, erection, testing project management, consultancy, supervision, and commissioning of Power Plant, GIS, and AIS high voltage substations ranging up to 500 kV HVAC & ±660kV HVDC more than ten years experience is with Siemens Saudi Arabia. He completed over 20 high voltage substation projects, Operation & Maintenance of Substations & Power plants in Pakistan and Saudi Arabia for different electric utilities, including Saudi Electricity Company (SEC), Saudi Aramco, SABIC, Marafiq, National Transmission & Dispatch Company (NTDC), WAPDA, and K-Electric. Also, he led testing and commissioning teams to implement electrical infrastructure projects for many industrial clients (Steel, Petrochemical, etc.) in Pakistan and Saudi Arabia.

Leave a Comment

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

  +  73  =  seventy five

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

EEP Hand-Crafted Video Courses

Check more than a hundred hand-crafted video courses and learn from experienced engineers. Lifetime access included.
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge