Purpose of Lock-out / Tag-out practice

Lock-Out / Tag-Out (LOTO) refers to the specific practices and guidelines to safeguard employees from the unexpected start-up, movement, activation, energizing, release of energy, etc of machinery, equipment, plant, systems during service, maintenance or inspection activities.

Lock out - Tag out practice and Seven steps that save lives
Lock out - Tag out practice and Seven steps that save lives (photo credit: ISHN.com)

In short: To protect people involved in a certain job from getting hurt by the system they work on.

Lock out tag out is a procedure which can be part of a safety procedure. See the second step of seven steps for safety – Disconnect and secure against reconnection or Jan De Nul High Voltage Access procedure step 5 (Take measures against starting up).

Lock-Out / Tag-Out is the safety procedure where the work area is marked properly and secured against the power reconnection with locks. The purpose of this is to prevent injury due to unexpected energizing or start up of machines and equipment, or the release of stored energy.


Field of Application //

  1. Shutting down (part) of machinery, equipment, and systems.
  2. An employee is required to remove or bypass machine guards or other safety devices.
  3. An employee is required to place any part of his or her body into a point of operation or into an area on a machine or piece of equipment where work is performed, or into the danger zone associated with the machine’s operation.
  4. Servicing and or maintaining of machines or equipment when the source of energy is electrical, mechanical, hydraulic, chemical, thermal, or otherwise energized.
  5. Constructing, installing, setting up, adjusting, inspecting, modifying, maintaining, including lubrication, cleaning or unjamming of machines or equipment, and making adjustments or tool changes where employees could be exposed to the unexpected energization of the equipment or release of hazardous energy.

When is a Lock-Out / Tag-Out procedure not needed

  1. Servicing and or maintenance of equipment performed during normal production operations if safeguarding provisions are effective in preventing worker exposure to hazards created by the unexpected energization or start up of machines or equipment, or the release of energy.
    Lockout tagout safety
    Lockout tagout safety


  2. Minor tool changes and adjustments.
  3. Minor servicing activities that take place during normal operations which are routine repetitive, and integral to the use of that equipment, as long as workers are effectively protected by alternative measures which provide effective machine safeguarding protection.
  4. Work on cord and plug connected equipment, if: The equipment is unplugged from the energy source and the authorized employee has exclusive control of the plug.

Limitations //

  1. Tag do not provide physical restraint.
  2. Tags should not be removed without authorization and are never to be bypassed, ignored or defeated.
  3. Tags are essentially warning devices affixed to energy isolating devices and do not provide the physical restraint on those devices that is provided by a lock.
  4. Tags must be legible and understandable by all employees.
    Danger! Do not operate safety tag
    Danger! Do not operate safety tag


  5. Tags and there means of attachment must be made of materials which will withstand the environmental conditions encountered in the workspace.
  6. Tags must be securely attached so that they cannot inadvertently or accidentally be detached during use.
  7. Locks must be substantial enough to prevent removal without the use of excessive force or unusual techniques such as with the use of bolt cutters or other metal cutting tools.
  8. If it is not possible to use lock-out devices, tags are located where the lock is supposed to be.
    Care must be taken that the tag out will provide protection at least as effective as a lock and will assure full personnel protection.
  9. The tag out can be made as effective as a lock when a circuit element is removed and isolated, a controlling switch is blocked, an extra disconnecting device is opened, or a valve handle is removed to reduce the potential for inadvertent energization while the tags are attached.

Seven steps that save lives

As an example of safety procedures we will discuss the safe working procedures used by HV field technicians these procedures are known under the name Seven steps that save lives. These steps are in a line with common standards for safe working procedures. It is recommended to do risk assessment throughout the work.

The step order can vary according to the procedure used (for example issuing permit to work):

  1. Identification of the work location
  2. Disconnection and securing against reconnection
  3. Protection against any other live parts
  4. Special precautions close to bare conductors
  5. Proving the installation dead
  6. Carrying out earthing and short-circuiting
  7. Issuing a permit to work

1. Identification of the work location

Identify the right work location and mark it clearly. The work location should have appropriate access and lighting. Non-authorized persons shall be restricted from entering the work location.

Lockout Tagout identification
Lockout Tagout identification

2. Disconnect and secure against reconnection

Disconnect all possible points of power supply. Secure the reconnection by means of a lock out and tag out procedure to ensure that electric equipment does not accidentally come alive. Take special care with transformers of which the secondary may be alive.


3. Protection against any other live parts

Put formal warning notices on panels or cabins you are not working on. Additional physical barriers must be applied (locks etc.) when live equipment is exposed. Recheck that you have the correct point of work.

When multiple cabinets are open you might by accident start working on the wrong cabinet.

4. Special precautions when close to bare conductors

There might arise a situation where you are working near potentially live parts, or there might be a situation where you can accidentally touch live parts when putting safety barriers.

Take special precautions (insulation gloves and or safety mats), especially if you are within a meter of a live connection. Take very special care on a moving vessel as the ship may be suddenly start rolling, so never use a safety stool as is a standard practice ashore.


5. Proving the installation is dead

The installation needs to be checked with appropriate testing gear. Test the instrument as for proper functioning first. Then verify with the test instrument that the installation is dead. Recheck the test instrument, only then you are sure your installation is dead.


6. Carrying out earthing and short circuiting

Earthing makes the installation free of residual charges and short-circuits the system in case of a fault current. Use only equipment designed for this purpose.

Reference // High voltage safety by ANTWERP MARITIME ACADEMY

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical engineering guides, research studies and much more! It helps you to shape up your technical skills in your everyday life as an electrical engineer.
More Information
author-pic

Edvard Csanyi

Electrical engineer, programmer and founder of EEP. Highly specialized for design of LV/MV switchgears and LV high power busbar trunking (<6300A) in power substations, commercial buildings and industry facilities. Professional in AutoCAD programming.

6 Comments


  1. MIGUEL BAS
    Sep 18, 2020

    Thanks for the information.


  2. Mahammad Karimulla
    May 04, 2020

    Useful information


  3. SYLVESTER MATI
    Apr 30, 2020

    This is exactly what I was looking for.Actually these articles are going to improve my Engineering skills largely.
    Thanks to developers of this portal


  4. Andy Wagg
    May 23, 2018

    Using a tool such as PCMD (PC Mimic Diagram by Schneider Electric) to model and simulate your electrical network in order to help create a plan of safe switching operations


    • Anand
      Aug 04, 2019

      @Andy Wagg , Where can I get PCMD software , is it free or need license

      Thanks for your knowledge sharing


  5. Mahmoud Motamedi
    Jun 16, 2017

    Many switchgear are made without possibility of installing lockout tagout. And there are risk of injurring personal because of this. What’s your suggestions for solving this problem? Like adding some parts to cubicle? Can you inform me about that. Or a company that’s specialist in this concept? Thanks a lot

Leave a Reply to Mahmoud Motamedi

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

  ⁄  three  =  three

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

Subscribe to Weekly Newsletter

Subscribe to our Weekly Digest newsletter and receive free updates on new technical articles, video courses and guides (PDF).
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge