Search

Premium Membership ♕

Save 50% on all EEP Academy courses with Enterprise Membership Plan and study specialized LV/MV/HV technical articles, guides and courses.

Home / Technical Articles / Maintenance Practices to be Followed for On-Site Generator Overhauling

Generator Overhauling

This discussion will focus on the on-site overhauling of a gas-powered generator, detailing the essential procedures for its enhancement. It is a common practice for utilities to test electrical assets periodically after a certain interval of time mainly as part of the activities when a complete turnaround of the plant takes place to replace, upgrade or identify any impending abnormalities within the plant equipments.

Maintenance Practices to be Followed for On-Site Generator Overhauling
Maintenance Practices to be Followed for On-Site Generator Overhauling

In case of electrical testing, previous tests serve as a blueprint, considering which the current testing results are assessed and a decision is made as to what further action should be taken.

The decision could end up either as “no further action seems to be necessary at this point after satisfactory results”, or “It is better to overhaul the machine and go for its refurbishment after degrading results”.

The former decision shouldn’t neglect the OEM or vendor’s guidelines on machine overhauling prescribed after a certain span.

Because we may obtain results without any signs of trouble as yet but a visual inspection of the actual physical state of the machine windings is critical in deciding that now is the time that it should be refurbished otherwise the accumulation of dust/fumes or other foreign particles could impact the winding drastically until the next cycle approaches.

Table of Contents:

  1. Overhauling of a Gas-Driven Generator On-Site
  2. Electrical Testing After Shutting Down the Unit
  3. Removal of Rotor
  4. Bearing Clearances
  5. Bearing Removal
  6. Inspection of All Parts
  7. Testing of Wedges of Stator Winding
  8. Generator Stator Refurbishment
    1. Partial Discharge Test
  9. A Peek into the Arrangement of Coils Inside Stator
  10. Mitigation of Partial Discharges
  11. Main Rotor and Exciter Generator
  12. Actions Post Re-assembly
    1. Phase Sequence Checking
    2. Generator Connections Verification
  13. Conclusion
  14. BONUS (PDF) 🔗 Download Handbook of Electric Machines and Drives

1. Overhauling of a Gas-Driven Generator On-Site

Here we’ll talk about the overhauling of a gas-driven generator on-site (pictured below) including the necessary steps required to better refurbish the unit. The actions required for the removal of the generator from its canopy/gen-turbine unit can be listed as,

  1. Removal of ventilation air duct
  2. Lube oil radiators
  3. Combustion air duct
  4. Electrostatic filters
  5. Generator Roof

Figure 1 – On-site gas-driven generator

On-site gas-driven generator
Figure 1 – On-site gas-driven generator

As far as the removal of generator-turbine coupling is concerned, the inadequate space surrounding it could require the removal of starting motor and shaft pump (connected to turbine) to better work around it. At the same time, the electrical team can work on removing the generator power and control cables from its junction box.

It is better to mark the control cables and their termination points on the connecting strips in the junction box so as not to err while reconnecting.

The control cables are used mainly for:

  • Winding temperature sensing RTDs
  • Bearing temperature sensing RTDs
  • Field ground (64F relay) sensing circuit
  • Auxiliary winding (in case of AREP excitation)
  • AVR output to exciter generator field (in case of brushless excitation)
  • Current and Potential transformers

Figure 2a – Picture showing generator power cables

Picture showing generator power cables
Figure 2a – Picture showing generator power cables

In order to avoid any hassle after start-up, it is better to note down the readings from all the sensors before shutting down the unit or after shutting down the unit while the control supply is still on so that any anomalous reading found after start-up could be better assessed.

For instance, if a bearing temperature sensor is known to be faulty and shows up an abnormal reading even before the shutdown, then any reading similar to that post-start-up could intrigue the control room operator who either doesn’t have any knowledge of such a sensor or assumes the faulty sensor has been replaced during shutdown when it actually hasn’t been and doesn’t confirm it with the maintenance personnel who also seem to have no idea about it.

So, just by referring to the readings straightaway prior to the shutdown, any hasty actions can be prevented.

Figure 2b – Picture showing generator control cables

Picture showing generator control cables
Figure 2b – Picture showing generator control cables

Go back to Content Table ↑


2. Electrical Testing After Shutting Down the Unit

Once the generator is shut down, do perform the electrical testing of entire set including the exciter generator as well in case of brushless excitation and note down the results so that the values could be compared with the ones obtained after refurbishment.

Following tests can be performed:

  1. PI, DAR and IR of stator winding
  2. IR test of rotor winding
  3. PD test of stator winding
  4. Winding resistance test of stator & rotor winding
  5. IR test of exciter generator field and armature winding
  6. Winding resistance test of exciter generator field and armature winding
  7. IR test of AREP windings
  8. Winding resistance test of AREP windings

Here generator power cables disconnected from generator can also be tested for insulation health.

Go back to Content Table ↑


3. Removal of Rotor

Once the generator has been freed from its canopy and moved to a suitable space, one conducive to the movement of overhead cranes, the next major step is the extraction of rotor from the generator. In the lead-up to the rotor removal, diode assembly mounted on NDE side, is removed first.

Figure 3 – Diode assembly

Diode assembly
Figure 3 – Diode assembly

Go back to Content Table ↑


4. Bearing Clearances

The next step is the removal of bearings from the generator. But before doing so, it is necessary to note down the bearing clearances on both sides. One can find out the bearing clearance by either of the two methods,


Method #1

In the first approach, a dial gauge is fixed onto machine shaft and the shaft is lifted upwards with an overhead crane. Then the shaft is released and the reading on the gauge is noted down.

Figure 4 – A dial gauge is fixed onto machine shaft and the shaft is lifted upwards with an overhead crane

A dial gauge is fixed onto machine shaft and the shaft is lifted upwards with an overhead crane
Figure 4 – A dial gauge is fixed onto machine shaft and the shaft is lifted upwards with an overhead crane

Method #2

Another way is to use a plastic gauge, a thin wire-like strip, which is placed onto the shaft and then the upper half of bearing is tightened onto it. Width of the deformed plastic gauge measured on a scale indicates the bearing clearance.

Figure 5 – Using a plastic gauge, a thin wire-like strip

Using a plastic gauge, a thin wire-like strip
Figure 5 – Using a plastic gauge, a thin wire-like strip

Go back to Content Table ↑


5. Bearing Removal

For removal of the bearing, the shaft of the machine is extended with a pipe on whichever side offers the ample space, while a support is provided underneath the pipe in order to support the shaft during and after bearing removal and help with the rotor removal subsequently. If the unit is a brushless excitation system, then it must be having a small exciter generator whose armature (rotor in this case) is mounted on the same shaft and field winding is bolted to the end cover.

Usually, there is very little airgap between field and armature of the exciter, even less than 2 mm.

Figure 6 – Extension Pipe Connected on DE Side

Extension Pipe Connected on DE Side
Figure 6 – Extension Pipe Connected on DE Side

Figure 7 – Generator Bearing Removal

Generator Bearing Removal
Figure 7 – Generator Bearing Removal

After the removal of bearing, the surface of the shaft where bearing is installed should be covered properly as shown in the attached picture,

Figure 8 – Properly Covered Bearing Area

Properly Covered Bearing Area
Figure 8 – Properly Covered Bearing Area

It is better to loosen the exciter field from the end cover so that when bearing is removed from either side, the field now simply rests on the exciter rotor (with an airgap twice the normal at the bottom between them) so that any probable exaggerated movement of shaft during bearing removal doesn’t culminate in exciter rotor pressing on the exciter field.

Similarly, a machine seal bolted to the end cover should be loosened first as well.

Membership Upgrade Required

This content is not available in your premium membership plan. Please upgrade your plan in order to access this content. You can choose an annually based Basic, Pro, or Enterprise membership plan. Subscribe and enjoy studying specialized technical articles, online video courses, electrical engineering guides, and papers.

With EEP’s premium membership, you get additional essence that enhances your knowledge and experience in low- medium- and high-voltage engineering fields.

Good to know 💡Save 50% on all courses with Enterprise membership plan.

Upgrade

Already a member? Log in here

Copyright Notice

This technical article is protected by U.S. and international copyright laws. Reproduction and distribution of PDF version of this technical article to websites such as Linkedin, Scribd, Facebook and others without written permission of the sponsor is illegal and strictly prohibited.

© EEP-Electrical Engineering Portal.

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical engineering guides, research studies and much more! It helps you to shape up your technical skills in your everyday life as an electrical engineer.
More Information
Umer Nasir - Author at EEP-Electrical Engineering Portal

Umer Nasir

I am an electrical engineer specializing in electrical power, with experience in the operation and maintenance of Low- and Medium-voltage electric machinery and switchgear, life assessment testing, troubleshooting, and root cause analysis of various failures associated with electrical machinery.
Profile: Umer Nasir

Leave a Comment

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

seven  ×  1  =  

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

EEP Hand-Crafted Video Courses

Check more than a hundred hand-crafted video courses and learn from experienced engineers. Lifetime access included.
Experience matters. Premium membership gives you an opportunity to study specialized technical articles, online video courses, electrical engineering guides, and papers written by experienced electrical engineers.