Search

Premium Membership ♕

Save 50% on all EEP Academy courses with Enterprise Membership Plan and study specialized LV/MV/HV technical articles & guides.

Home / Technical Articles / Dos and don’ts in site testing and commissioning distribution and transmission plants

The art of testing and commissioning

The objective of the site inspection and test plan for testing and commissioning is to establish a comprehensive framework for conducting site testing and commissioning activities. It’s as simple as that! The site testing and commissioning of a transmission or distribution plant are the final procedures conducted to verify the proper functioning of the plant and its compliance with stated specifications.

Dos and dont's in site testing and commissioning distribution and transmission plants
Dos and dont's in site testing and commissioning distribution and transmission plants (photo credit: Warna RS Sdn. Bhd.)

Typically, the equipment undergoes factory testing, and it is the responsibility of the commissioning engineers to ensure proper assembly and installation of the equipment. The primary goals of the site inspection and test plan for testing and commissioning are:

The goal number one is verification of the proper installation of the specified equipment. Second goal is the confirmation of the correct functioning of the equipment and absence of damage during shipment or installation. The third goal would be to ensure that the desired operations/functions are achieved with the selected design.

Fourth and not less important goal is to acquire a collection of as-built drawings and test data for future reference in order to facilitate alterations and periodic maintenance.

Prior to conducting testing and commissioning, it is essential that the test procedures and records have been approved by the client and that the commissioning engineer possesses the appropriate mindset to carry out the tasks in a systematic and professional manner.

Ok, let’s get into the details!

Table of Contents:

  1. Personnel and Responsibilities
  2. Safety and potential acidents:
    1. Requirements for the Health & Safety Checklist
    2. Electric shock (have your eyes on the back)
    3. Working method and tension (nervousness and mistakes)
    4. Customer’s and third party personnel
    5. Work and operational verifications (safety guarantees):
      1. Work verification
      2. Operational verification
    6. Operational responsibility
    7. Disconnection, temporary safety earthing:
      1. Disconnection
      2. Temporary safety earthing
      3. Barriers
      4. Clothing (no fashion permitted!)
    8. Measuring equipment and tools:
      1. Fuses
      2. Insulated tools
    9. Induced voltages (invisible danger)
    10. Current transformers (know how to handle them)
    11. Voltage transformers (can be damaged)
    12. Power capacitors and high voltage cables
    13. Low voltage switchgear
    14. Batteries
    15. Convertor
    16. Fuses
    17. Electrically operated equipment
  3. BONUS (PDF) 🔗 Download Substation Test and Commissioning Manual

1. Personnel and Responsibilities

Commissioning Coordinator:

A Commissioning Coordinator is tasked with coordinating all activities associated with testing and commissioning, as well as executing the site inspection and test plan for these processes.


Testing and Commissioning Engineer:

A Testing and Commissioning Engineer is accountable for conducting tests and commissioning equipment, while ensuring adherence to the appropriate processes. After finishing all of the tests, he will sign the corresponding test record and ask any witnessing representative to do the same.

The Testing and Commissioning Engineer is accountable for the following:

The Commissioning Officer will prepare a Commissioning Staging Plan during the project development period.

The staging plan will provide a comprehensive description of the intended arrangements for the substation, distribution, and transmission/sub-transmission primary plant designs at each stage of the commissioning process. The commissioning staging information should be utilized throughout the creation of design specifications to guarantee that designs for all primary plant, secondary systems, and protective systems are developed for each of the intended commissioning stages.

The Commissioning Staging Plan is a comprehensive document that outlines the intended commissioning staging in a broad and sweeping manner.

The Commissioning Officer is accountable for the creation of a Commissioning Outage Plan. This plan will outline the specific plant and system outages needed to successfully carry out the scheduled commissioning stages of the project.

During the construction of the outage plan, it is necessary to have close contact with the Project Leadership Team to effectively manage network risks during commissioning.

Figure 1 – Testing and commissioning engineers in action of testing power transformer at night

Testing and commissioning engineers in action of testing power transformer at night
Figure 1 – Testing and commissioning engineers in action of testing power transformer at night (photo credit: Warna RS Sdn. Bhd.)

Another responsibility of Commissioning Engineer is to create Inspection and Test Plans and Test Reports. These documents serve as quality control measures and outline the specific testing requirements for primary plant and secondary systems.

The designated Commissioning Engineer will have the responsibility of creating the Inspection and Test Plans and Test Reports for every commissioning stage throughout the initial phase of project implementation.

Go back to Content Table ↑


2. Safety and potential acidents

From the safety point of view, the testing and commissioning of distribution and transmission plants is often done under hazardous conditions. The risk of accidents must always be taken into consideration and the testing and commissioning personnel have to be fully aware of the dangers that exist and should know how to conduct their work to avoid such hazards.


2.1 Requirements for the Health & Safety Checklist

The manufacturer’s supervisor is required to conduct a comprehensive assessment of the health and safety conditions in the work area. Consequently, he completes the health and safety checklist for installation. In cases when shortcomings are identified, it is necessary to complete the comprehensive checklist.

Unless any faults are found, it is not necessary to complete the full checklists.

Go back to Content Table ↑


2.2 Electric shock

Undoubtedly, the most significant hazard linked to the testing and commissioning of electric plant is the possibility of electric shock. Electric shock accidents are particularly unique since the individuals involved rarely receive any advance notice, as the risk cannot be detected by human senses.

Merely making brief touch with a “energized” component of a system, even if it does not exhibit any indications of danger through sound or motion, is sufficient to result in a severe mishap.

The Five-Safety Roules:

  1. Disconnecting
  2. Securing against reclosing
  3. Testing for absence of voltage
  4. Earthing and short-circuiting
  5. Covering or fencing off adjacent live parts

Figure 2 – Engineer performing testing of HV capacitor banks

Engineer performing testing and commissioning of HV capacitor banks
Figure 2 – Engineer performing testing and commissioning of HV capacitor banks (photo credit: Warna RS Sdn. Bhd.)

Go back to Content Table ↑


2.3 Working method and tension

(Nervousness and mistakes)

The testing and commissioning of a plant frequently needs to be completed within a tight timeframe and involves multiple individuals from various companies. Testing and commissioning professionals must consider two possible causes of accidents:

  • High-pressure scenarios that require immediate action rather than systematic deliberation.
  • A tense scenario arises during the energizing phase, particularly when one partner is uninformed of the actions being taken by the other.

The testing and commissioning people should always avoid being swayed by client expectations, economic pressure, or any other factors that could compromise the safety of the personnel.

Throughout all procedures involving the supply of energy, the individual (customer/consulting engineer) in charge of operating the facility is responsible for providing all orders and instructions related to operations, connections, temporary grounding, and other relevant matters.

During the energizing sequence, it is necessary for all communication between the individual in question and manufacturer’s testing and commissioning professionals to be conducted exclusively through a single person, namely the chief commissioning engineer. This measure is implemented to avoid any potentially deadly misunderstandings.

The manufacturer’s chief commissioning engineer will provide instructions on how to take measurements and perform necessary fault-finding procedures in electrified equipment. This is done to reduce the danger of mishaps that may occur when there is uncertainty about responsibilities.

Membership Upgrade Required

This content is not available in your premium membership plan. Please upgrade your plan in order to access this content. You can choose an annually based Basic, Pro, or Enterprise membership plan. Subscribe and enjoy studying specialized technical articles, online video courses, electrical engineering guides, and papers.

With EEP’s premium membership, you get additional essence that enhances your knowledge and experience in low- medium- and high-voltage engineering fields.

Did you know?Save 50% on all video courses by purchasing Enterprise plan.

Upgrade

Already a member? Log in here

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical engineering guides, research studies and much more! It helps you to shape up your technical skills in your everyday life as an electrical engineer.
More Information
author-pic

Edvard Canji

Electrical engineer, programmer and founder of EEP. Highly specialized for design of LV/MV switchgears and LV high power busbar trunking (<6300A) in power substations, commercial buildings and industry facilities. Professional in AutoCAD programming.

Leave a Comment

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

five  +  two  =  

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

EEP Hand-Crafted Video Courses

Check more than a hundred hand-crafted video courses and learn from experienced engineers. Lifetime access included.
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge