Simple Spot Network Systems

The AC secondary network system is the system that has been used for many years to distribute electric power in the high-density, downtown areas of cities, usually in the form of utility grids. Modifications of this type of system make it applicable to serve loads within buildings.

Spot network systems for distribution of electric power in downtown areas of cities
Spot network systems for distribution of electric power in downtown areas of cities

The major advantage of the secondary network system is continuity of service. No single fault anywhere on the primary system will interrupt service to any of the system’s loads.

Most faults will be cleared without interrupting service to any load.

Another outstanding advantage that the network system offers is its flexibility to meet changing and growing load conditions at minimum cost and minimum interruption in service to other loads on the network.

In addition to flexibility and service reliability, the secondary network system provides exceptionally uniform and good voltage regulation, and its high efficiency materially reduces the costs of system losses.

Three major differences between the network system and the simple radial system account for the outstanding advantages of the network.

First, a network protector is connected in the secondary leads of each network transformer in place of, or in addition to, the secondary main breaker, as shown in Figure 2.

Also, the secondaries of each transformer in a given location (spot) are connected together by a switchgear or ring bus from which the loads are served over short radial feeder circuits. Finally, the primary supply has sufficient capacity to carry the entire building load without overloading when any one primary feeder is out of service.

A network protector is a specially designed heavy-duty air power breaker, spring close with electrical motor-charged mechanism, with a network relay to control the status of the protector (tripped or closed).

Eaton’s CM52 network protector - Fully interlocked, dead-front, 4 position draw-out design available with internally or externally mounted fuses
Figure 1 – Eaton’s CM52 network protector – Fully interlocked, dead-front, 4 position draw-out design available with internally or externally mounted fuses

The network relay is usually a solid-state microprocessor-based component integrated into the protector enclosure that functions to automatically close the protector only when the voltage conditions are such that its associated transformer will supply power to the secondary network loads.

It also serves to automatically open the protector when power flows from the secondary to the network transformer.

The purpose of the network protector is to protect the integrity of the network bus voltage and the loads served from it against transformer and primary feeder faults by quickly disconnecting the defective feeder-transformer pair from the network when backfeed occurs.

The simple spot network system resembles the secondary-selective radial system in that each load area is supplied over two or more primary feeders through two or more transformers.

In network systems, the transformers are connected through network protectors to a common bus, as shown in Figure 2, from which loads are served.

Because the transformers are connected in parallel, a primary feeder or transformer fault does not cause any service interruption to the loads.

The paralleled transformers supplying each load bus will normally carry equal load currents, whereas equal loading of the two separate transformers supplying a substation in the secondary-selective radial system is difficult to obtain.

Three-Source Spot Network
Figure 2 – Three-Source Spot Network

The interrupting duty imposed on the outgoing feeder breakers in the network will be greater with the spot network system.

The optimum size and number of primary feeders can be used in the spot network system because the loss of any primary feeder and its associated transformers does not result in the loss of any load even for an instant.

In spite of the spare capacity usually supplied in network systems, savings in primary switchgear and secondary switchgear costs often result when compared to a radial system design with similar spare capacity.

This occurs in many radial systems because more and smaller feeders are often used in order to minimize the extent of any outage when a primary fault event occurs.

In spot networks, when a fault occurs on a primary feeder or in a transformer, the fault is isolated from the system through the automatic tripping of the primary feeder circuit breaker and all of the network protectors associated with that feeder circuit.

This operation does not interrupt service to any loads.

After the necessary repairs have been made, the system can be restored to normal operating conditions by closing the primary feeder breaker. All network protectors associated with that feeder will close automatically.

The chief purpose of the network bus normally closed ties is to provide for the sharing of loads and a balancing of load currents for each primary service and transformer regardless of the condition of the primary services. Also, the ties provide a means for isolating and sectionalizing ground fault events within the switchgear network bus, thereby saving a portion of the loads from service interruptions, yet isolating the faulted portion for corrective action.

The use of spot network systems provides users with several important advantages.

First, they save transformer capacity. Spot networks permit equal loading of transformers under all conditions. Also, networks yield lower system losses and greatly improve voltage conditions.

The voltage regulation on a network system is such that both lights and power can be fed from the same load bus. Much larger motors can be started across-the-line than on a simple radial system.

This can result in simplified motor control and permits the use of relatively large low voltage motors with their less expensive control.

Finally, network systems provide a greater degree of flexibility in adding future loads. They can be connected to the closest spot network bus.

Spot network systems are economical for buildings that have heavy concentrations of loads covering small areas, with considerable distance between areas, and light loads within the distances separating the concentrated loads.

They are commonly used in hospitals, high rise office buildings, institutional buildings or laboratories where a high degree of service reliability is required from the utility sources.

Spot network systems are especially economical where three or more primary feeders are available. Principally, this is due to supplying each load bus through three or more transformers and the reduction in spare cable and transformer capacity required. They are also economical when compared to two transformer double-ended substations with normally opened tie breakers.

Emergency power should be connected to network loads downstream from the network, or upstream at primary voltage, not at the network bus itself.


Bus configuration for a 3-unit commercial spot network

Figure 3 shows the bus configuration for a three-unit commercial spot network. Again, the ground return neutral bus is required which has only one point of connection to the grounding conductor.

Single-Line Diagram for Two-Unit Spot Network - Protectors as Mains
Figure 3 – Single-Line Diagram for Two-Unit Spot Network – Protectors as Mains

Selective tripping is achieved in the same fashion as the double-ended network substation with ground fault relay for tie breaker (GFR-T) sensing ground current and operating the 86T device which then opens both Tie breakers. The ground relays GFR-1, GFR-2 and GFR-3 will only sense ground current after the Tie 86 lockout is energized and the tie breakers are open.

Interlocking auxiliary contacts on the 86-T with the GFR circuits guarantees this selective tripping and ensures the user that ground currents are accurately
measured.

The ampacity of the ground return neutral bus must meet the minimum requirements of the neutral bus.

It is prudent to size the ground return neutral bus the same size as the phase bus, because the ground and neutral carry fault currents during abnormal events.

The space required by the ground sensors and connecting buswork can be accommodated easily in two-unit spot networks. However, on three-and four-unit systems, the extensive structure-to-structure insulated ground bus plus the normal phase, neutral and ground buses can reduce the usage of four breaker cells in the switchgear to three. Vendor designs vary on this issue.

The ampacity of the phase and neutral buswork must meet the gross demand plus spare capacity for growth as stipulated by the National Electrical Code (NEC) for the loads served.

If each transformer on a two-unit spot network has been sized with 100% redundancy, then each protector and load buswork should be rated to carry the entire load from one primary feeder and one transformer.

Three-unit spot networks can reduce the redundancy to 50% for the same loads because two units remain in service. Four-unit spot networks may reduce the redundancy to 33%, unless the loads need to be served from two remaining services in which case 100% redundancy is still required.

Sources:

  1. Power distribution systems by Eaton
  2. Spot Network Equipment by Eaton

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical engineering guides, research studies and much more! It helps you to shape up your technical skills in your everyday life as an electrical engineer.
More Information
author-pic

Edvard Csanyi

Electrical engineer, programmer and founder of EEP. Highly specialized for design of LV/MV switchgears and LV high power busbar trunking (<6300A) in power substations, commercial buildings and industry facilities. Professional in AutoCAD programming.

One Comment


  1. Anoop Kumar Sharma
    Apr 24, 2019

    Please guide me about how to calculate size of earthing strip in system. Fault level of HT and LT Panels.

Leave a Reply to Anoop Kumar Sharma

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

  −  four  =  2

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

Subscribe to Weekly Newsletter

Subscribe to our Weekly Digest newsletter and receive free updates on new technical articles, video courses and guides (PDF).
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge