Search

Premium Membership ♕

Limited Time Offer: Save 15% on PRO Plan with discount code: LRN15 and study specialized LV/MV/HV technical articles and studies.

Home / Technical Articles / The art of the switchyard design: Case study of a 220/33 kV 200 MW wind farm

Design of a 220/33 kV switchyard

This technical article continues with the switchyard design series by studying the case of the 220/33 kV 200 MW wind farm switchyard in which the design steps are put into practice. Previously, a switchyard design methodology was addressed and it’s advisable to read it first. There are many different ways in which a switchyard can be designed. Each way would have some advantages and disadvantages.

The art of the switchyard design: Case study of a 220/33 kV 200 MW wind farm
The art of the switchyard design: Case study of a 220/33 kV 200 MW wind farm

This methodology is a structure that follows the work of the switchyard’s experts for many decades. Groundworks represent the first stage, where basic engineering works are settled. This includes the voltage selection, grid substation through which the power is transmitted to the network, and the factors for selecting the substation location are elaborated.

The underlying project delivery method determines the extent to which an organization details the design. If an organization decides on tendering the design (design-bid-build), this stage is enough.

If the organization, however, is into in-house detailed design, the next phase is the detailed engineering design.

The detailed design starts with preparing the single-line diagram by having an overview of all the switchyard equipment types. This overview considers reliability measures, different busbar configurations, centralized/decentralized architecture, and many others. The actual main equipment sizing and selections along with the auxiliary system design follow.

Then, the execution phases come into play in which the plan layout, sectional views, grounding design, cable routes, lightning, and erection key diagrams (clamps & connectors) are all presented. The secondary engineering comes at last, where protection concept, relay settings, protection SLD, cable termination and schedule, and many others are finalized.

Table of Contents:

  1. Case Study
    1. Preparation of Single-Line Diagram
  2. Equipment Sizing
    1. Power Transformers 2×100 MVA
    2. Busbar and Lines
    3. Circuit Breakers
    4. Disconnectors
    5. Lightning Arrestors
    6. Auxiliary System
    7. Instrument Transformers (CTs and PTs)
  3. Switchyard Plan Layout
  4. Grounding Design
  5. Lightning Protection
  6. Control and Protection

1. Case Study

A wind power plant of an installed capacity of 200 MW is to be integrated into the network through a transmission substation (switchyard) that is linked to the network through a selected grid substation. The grid substation is at 220 kV level. The 220 kV level is suitable for the 200 MW output power as per the local guidance that restricts the maximum power for a given voltage level.

Recall the voltage formula given in the previous article:

Formulae

In this formula, L is the line length in kilometres, P is the transmitted power in kW, pf is the power factor, and N is the number of circuits, and the given information is as follows:

  • The distance between wind farm and switchyard is 10 km.
  • The power is 200 MW.
  • The power factor is 0.95.
  • The number of circuits is two.
The calculated voltage is about 145 kV, and one needs to go for the next higher voltage level if it does not fall into a standard voltage level, which is 220 kV in this case.

Wind power comprises hub (rotor) blades that are 120 degrees in phase shift. These blades are linked to an induction generator and a step-up transformer contained in a nacelle. The hub and the nacelle are mounted on top of a tower that is in the range of 90-110 meters in height.

The arrangement inside wind powers varies as in Figure 1, where the transformer is located at the bottom of the wind power.

Figure 1 – Wind power connections

Wind power connections
Figure 1 – Wind power connections

In this project, the generation voltage is 690 V that is stepped up to 33 kV, and each wind power generates 2 MW, so the output current is about 37 A. The aggregate output current is 3700 A for the designed capacity of 200 MW.

The wind power industry has an oligopoly market structure in which few firms dominate the industry. Mainly, three organizations exist in this industry: Suzlon, Siemens Gamesa, and Vestas.

The design, execution, and commissioning are out of the scope of the switchyard design office, and what is important is the output cable(s) reaching the transmission substation.

Go back to Content Table ↑


1.1. Preparation of Single-Line Diagram

The very first activity at this stage is to select the number of incoming cables from the wind farm in accordance with two criteria-namely, reliability and conductor size and weight. The IEEE Gold book explains the reliability evaluation procedure required for any study including the configuration of the incoming cables.

Moreover, a designer should consider the amount of power loss whose impact is affordable in case of any cable failure. Different options are listed in Table 1 along with the impact of one incomer failure. It is clear that as the number of incomers lines increase the reliability increases but at a higher cost.

Without going for detailed reliability computations, designers selected the fourth option (10 lines) as the optimal arrangement.

Table 1 – Number of incomers versus power lost

Number of incomersPower lost (MW)
1200
2100
540
1020

The conductor size and weight is another determining factor in setting the number of incomer lines. The one incomer option that feeds 3700 A mandates using quad Bersimis conductors that are too heavy for the 33 kV available towers. Similarly, other options do not make any practical feasibility nor economic feasibility except for the last one (i.e. 10 lines).

This selection enables us to go for the Wolf or the Panther conductor size (preferable in 33 kV) in which the gross weight is less than 1 ton/km/tower. Hence, the conductor size and weight go hand in hand with the reliability study for compatibility purposes.

Premium Membership Required

This technical article/guide requires a Premium Membership. You can choose an annually based Plus, Pro, or Enterprise membership plan. Subscribe and enjoy studying specialized technical articles, online video courses, electrical engineering guides, and papers. With EEP’s premium membership, you get additional essence that enhances your knowledge and experience in low- medium- and high-voltage engineering fields.

Check out each plan’s benefits and choose the membership plan that works best for you or your organization.

Limited time offer! – Save 15% on Pro Membership Plan with discount code LRN15

Log In »Purchase »

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical engineering guides, research studies and much more! It helps you to shape up your technical skills in your everyday life as an electrical engineer.
More Information
author-pic

Salem Alshahrani

Electrical engineer (BEE & Meng). Specialized in substation design, especially in LV/MV switchgears and transformers. Passionate in power system planning, analysis, and stability studies.

Leave a Comment

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

  ⁄  two  =  one

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

Subscribe to Weekly Newsletter

Subscribe to our Weekly Digest newsletter and receive free updates on new technical articles, video courses and guides (PDF).
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge