Search

Premium Membership ♕

Save 50% on all EEP Academy courses with Enterprise Membership Plan and study specialized LV/MV/HV technical articles & guides.

Home / Technical Articles / My worst experience in testing and commissioning power transformers (and how I fixed things up)

Transformer commissioning

Reliable and secure electric power delivery is dependent on power transformers’ reliability that is enhanced significantly by sound test plans. These test plans shall be prepared by both manufacturers and end-users to develop thorough and effective plans and specifications. The plan and specifications developers must account for several factors like anticipated environmental conditions, grounding types, exposure to lightning, and switching transient conditions.

My worst experience in testing and commissioning power transformers (and how I fixed things up)
My worst experience in testing and commissioning power transformers (and how I fixed things up)

The nominal rating specifications are not the only specifications that should be included, but also special ratings like impedance, sound level, or otherwise shall be considered in the test plan and formulated in the specifications.

It is vital to select the set of test plans and specifications of correct test levels that suit the transformer application so as to have an overall reliable power system.

Transformers are subjected to a number of test plans in order to achieve:

  • Compliance with user specifications
  • Quality and reliability assessment
  • Design calculation verification
  • Compliance with applicable industry standard
This technical article discusses a comprehensive approach to conduct transformer commissioning successfully. The set of standards employed, test classes, and test sequence shall be identified beforehand. The pre-commissioning phase is vital in finding any issues prior to engaging in the commissioning process.

Delays are expected during the commissioning phase due to many reasons, but this can be enhanced substantially by imposing a systematic procedure. Moreover, few case studies are briefly discussed to shed light on some common problems that are likely to be encountered during the commissioning.

Some of these cases could have been avoided by following simple visual inspection, so it cannot be emphasized much to follow a well-written procedure.

Table of Contents:

  1. ANSI standards for power transformers
  2. Classification of Tests
  3. Sequence of Tests
  4. Transformer Pre-Commissioning
  5. Transformer Commissioning:
    1. Sweep Frequency Response Analysis (SFRA)
    2. Dielectric Response Frequency (DFR)
    3. Transformer Differential Protection
  6. Case Studies
    1. Oil Analysis and Insulators
    2. Oil Level Problem
    3. Problems in Transformer Differential Protection
  7. BONUS – Standards used for power transformers (PDF)

1. ANSI standards for power transformers

ANSI standards for power transformers are provided in the C57 series of standards. Power transformers, as well as distribution transformers general requirements, are given in the following two standards:

  1. IEEE C57.12.00: IEEE Standard General Requirements for Liquid-Immersed Distribution, Power, and Regulating Transformers
  2. IEEE C57.12.90: IEEE Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers; and Guide for Short-Circuit  Testing of Distribution and Power Transformers (ANSI)

There are several other standards in the ANSI C57 series for transformers that cover certain specific products and special applications. They also include guides, recommended practices, and tutorials. Indeed, these documents are of great importance for readers who need detailed information on power and distribution transformers testing.

The standards mentioned above are very important references because they serve as an effective communication medium between manufacturers and users. They identify critical features, provide minimum requirements for safe and reliable operation, and serve as valuable references of technical information.

Factory Acceptance Test(FAT) for 2 unit transformer 132kV 90MVA & 2 unit 33kV 30MVA
Figure 0 – Factory Acceptance Test(FAT) for 2 unit transformer 132kV 90MVA & 2 unit 33kV 30MVA (photo credit: Abang Abdul Rahman via Twitter)

Go back to Contents Table ↑


2. Classification of Tests

Power transformers tests are classified according to ANSI and IEEE standards into routine tests, design tests, and other tests. Other tests are applied to ensure the transformer quality measures throughout the transformer production cycle stages. Power transformer test categories are listed in Table 1.

Table 1 – Transformer test categories

No.Transients
1Lightning impulse:
– Full wave
– Chopped wave
– Steep wave
2Switching impulse

No.Low (Power) Frequency
1Applied voltage
2Single-phase induced
3Three-phase induced
4Partial discharge

No.Tests of Performance Characteristics
1No-load loss
2Excitation current %
3Load loss
4Impedance %
5Zero-sequence impedance
6Ratio test
7Short-circuit test

No.Thermal Tests
1Winding resistance
2Heat run test:
– Oil rise
– Winding rise
– Hottest-spot rise
3Overload heat run
4Gas in oil
5Thermal scan

No.Other Transformer Tests
1Insulation capacitance and dissipation factor
2Sound-level tests
310-kV excitation current Megger
4Core ground
5Electrical center
6Recurrent surge
7Dew point
8Core loss before impulse
9Control-circuit test
10Test on a series transformer
11LTC tests
12Preliminary ratio tests
13Test on bushing CT
14Oil preservation system

The stage at which these tests are performed differ; some tests are applied before assembling the core and coil inside the tank, and some tests are performed after fully assembling the transformer and make it ready for final testing. This final testing term is not really final testing, as additional tests are performed just before shipment besides commissioning tests at customer sites.

NOTE! In all of these tests, the test levels and the accept/reject criteria are of prime importance in the jointly developed test plan between the manufacturer and the transformer client.

Premium Membership Required

This technical article/guide requires a Premium Membership. You can choose an annually based Plus, Pro, or Enterprise membership plan. Subscribe and enjoy studying specialized technical articles, online video courses, electrical engineering guides, and papers. With EEP’s premium membership, you get additional essence that enhances your knowledge and experience in low- medium- and high-voltage engineering fields.

Check out each plan’s benefits and choose the membership plan that works best for you or your organization.

Good To Know!Save 50% on all video courses by purchasing Enterprise plan.

Log In »Purchase »

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical engineering guides, research studies and much more! It helps you to shape up your technical skills in your everyday life as an electrical engineer.
More Information
author-pic

Salem Alshahrani

Electrical engineer (BEE & Meng). Specialized in substation design, especially in LV/MV switchgears and transformers. Passionate in power system planning, analysis, and stability studies.

Leave a Comment

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

  −  nine  =  one

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

Subscribe to Weekly Newsletter

Subscribe to our Weekly Digest newsletter and receive free updates on new technical articles, video courses and guides (PDF).
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge