Before any testing of low voltage electrical installations (and equipment) is carried out, a detailed physical inspection must be made to ensure that everything is to a relevant National standard, erected/installed in compliance with the IEE Regulations and not damaged in such a way that it could cause danger.

18 Initial Checks Of Electrical Installations Every Electricain MUST Perform
18 Initial Checks Of Electrical Installations Every Electricain MUST Perform

In order to comply with these requirements, the Regulations give a checklist of items that, where relevant, should be inspected. However, before such an inspection, and test for that matter, is carried out, certain information must be available to the verifier.

This information is the result of the ‘Assessment of General Characteristics’ required by IEE Regulations (Part 3, sections 311, 312 and 313), together with drawings, charts and similar information relating to the installation. For domestic electrical installations, these diagrams and charts are usually in the form of a simple schedule.

Interestingly, one of the items on the checklist isthe presence of diagrams, instructions and similar information. If these are missing, there is a deviation from the Regulations.

Another item on the list is the verification of conductors for current carrying capacity and voltage drop in accordance with the design. How could this be verified without all the information?

A 32A type B circuit breaker protecting a length of 4.0 mm2 conductor may look reasonable, but is it correct and, unless you are sure, are you prepared to sign to say that it is?


General testing checklist

Let us look then at the general content of the checklist:


Check #1 – Connection of conductors

Are terminations electrically and mechanically sound? Is insulation and sheathing removed only to a minimum to allow satisfactory termination?


Check #2 – Identification of conductors

Are conductors correctly identified in accordance with the regulations?

Labeling of terminals and conductors
Labeling of terminals and conductors (photo credit: barnsleyelectrical.co.uk)

Check #3 – Routing of cables

Are cables installed such that account is taken of external influences, such as mechanical damage, corrosion and heat?


Check #4 – Conductor selection

Are conductors selected for current carrying capacity and voltage drop in accordance with the design?


Check #5 – Connection of single pole devices

Are single pole protective and switching devices connected in the line conductor only?

Electrical panel
Electrical panel (photo credit: electricianstruro.com)

Check #6 – Accessories and equipment

Are all accessories and items of equipment correctly connected?


Check #7 – Thermal effects

Are fire barriers present where required and protection against thermal effects provided?


Check #8 – Protection against shock

What methods have been used to provide protection against electric shock?


Check #9 – Mutual detrimental influence

Are wiring systems installed so that they can have no harmful effect on non-electrical systems or so that systems of different currents or voltages are segregated where necessary?


Check #10 – Isolation and switching

Are the appropriate devices for isolation and switching correctly located and installed?


Check #11 – Undervoltage

Where undervoltage may give rise for concern, are there protective devices present?


Check #12 – Protective devices

Are protective and monitoring devices correctly chosen and set to ensure automatic disconnection and/or overcurrent?

Protective devices - Miniature circuit breakers (MCB)
Protective devices – Miniature circuit breakers (photo credit: electricalsafetycertificate.co.uk)

Check #13 – Labelling

Are all protective devices, switches (where necessary) and terminals correctly labelled?


Check #14 – External influences

Have all items of equipment and protective measures been selected in accordance with the appropriate external influences?


Check #15 – Access

Are all means of access to switchgear and equipment adequate?


Check #16 – Notices and signs

Are danger notices and warning signs present?

Circuit breaker lockout tag
Circuit breaker lockout tag (photo credit: lockoutstore.com)

Check #17 – Single line diagrams / Wiring schemes

Are diagrams, instructions and similar information relating to the installation available?


Check #18 – Erection methods

Have all wiring systems, accessories and equipment been selected and installed in accordance with the requirements of the Regulations? Are fixings for equipment adequate for the environment?

Once all the relevant items have been inspected, providing there are no defects that may lead to a dangerous situation when testing, the actual testing procedure can start.

Reference // Electric Wiring: Domestic – Brian Scaddan IEng, MIET

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical engineering guides, research studies and much more! It helps you to shape up your technical skills in your everyday life as an electrical engineer.
More Information
author-pic

Edvard Csanyi

Electrical engineer, programmer and founder of EEP. Highly specialized for design of LV/MV switchgears and LV high power busbar trunking (<6300A) in power substations, commercial buildings and industry facilities. Professional in AutoCAD programming.

4 Comments


  1. Zubair hashmk
    Mar 07, 2019

    HI. thats great explaination but i like to discuss about glands requirements? I understand that if is mandatory cor power cabld that one gland one cable? But what about numerous controls cable or we can create a rectangle cut with rubber ipx rating insulation to protect wires from damage.


  2. Yanal Naghawi
    Jul 26, 2018

    Great information, I’m a professional electrition and I highly appreciate the information you provide, I suggest that you provide more information about how to do safety tests for houses insulation.


  3. Barklign Ambachew
    Apr 20, 2018

    Dear sir,Csanyi;
    you do the best job for all around the world so that many Electricians can improve their ability of areas of electrical and technology fields.
    Just I am an Electrical and Computer Engineering student, interested in all what you provide in this site.
    I would like to thank you at all.


  4. Tesfaye Abebe
    Mar 14, 2016

    Dear Sir,
    I would like to thank you very much. I am one of the beneficiary of this web site. please keep it up.

    Tesfaye Abebe.
    Ethiopia.

Leave a Reply to Barklign Ambachew

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

seven  ×  1  =  

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

Subscribe to Weekly Newsletter

Subscribe to our Weekly Digest newsletter and receive free updates on new technical articles, video courses and guides (PDF).
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge