High voltage substations are points in the power system where power can be pooled from generating sources, distributed and transformed, and delivered to the load points. Substations are interconnected with each other so that the power system becomes a meshed network.

5 good circuit schemes to avoid HV substation outage
5 good circuit schemes to avoid HV substation outage (on photo: Compact gas insulated switchgear (GIS) by Siemens in Berlin; credit: SIEMENS)

This increases the reliability of the power supply system by providing alternate paths for the flow of power to take care of any contingency (by selecting the most suitable circuit schemes) so that power delivery to the loads is maintained and the generators do not face any substation outage.

The high voltage substation is a critical component in the power system, and the reliability of the power system depends upon the substation. Therefore, the circuit configuration of the high voltage substation has to be selected carefully.

Busbars are the part of the substation where all the power is concentrated from the incoming feeders, and distributed to the outgoing feeders. That means that the reliability of any high voltage substation depends on the reliability of the busbars present in the power system.

An outage of any busbar can have dramatic effects on the power system. An outage of a busbar leads to the outage of the transmission lines connected to it. As a result, the power flow shifts to the surviving healthy lines that are now carrying more power than they are capable of.

This leads to tripping of these lines, and the cascading effect goes on until there is a blackout or similar situation. The importance of busbar reliability should be kept in mind when taking a look at the different busbar systems that are prevalent.

  1. Single-busbar scheme (1 BB)
  2. Double-busbar scheme (2 BB)
  3. Double circuit-breaker scheme (2 CB)
  4. One-breaker-and-a-half scheme (1.5 CB)
  5. 3-phase busbar scheme (3 BB)

1. Single-busbar scheme (1 BB)

The applications of this simple scheme are distribution and transformer substations, and feeding industrial areas (see figure 1). Because it has only one busbar and the minimum amount of equipment, this scheme is a low-cost solution that provides only limited availability.

In the event of a busbar failure and during maintenance periods, there will be an outage of the complete substation. To increase the reliability, a second busbar has to be added.

Special single busbar, H-scheme (1 BB)
Figure 1 – Special single busbar, H-scheme (1 BB)

Go back to Circuit Schemes ↑


2 .Double-busbar scheme (2 BB)

The more complex scheme of a double-busbar system gives much more flexibility and reliability during operation of the substation (see figure 2).

For this reason, this scheme is used for power distribution and transformer substations at the nodes of the power supply system.

It is possible to control the power flow by using the busbars independently, and by switching a feeder from one busbar to the other. Because the busbar disconnectors are not able to break the rated current of the feeder, there will be a short disruption in power flow.

Double-busbar scheme (2 BB)
Figure 2 – Double-busbar scheme (2 BB)

Go back to Circuit Schemes ↑


3. Double circuit-breaker scheme (2 CB)

To have a load change without disruption, a second circuit- breaker per feeder has to be used. This is the most expensive way to solve this problem. In very important feeders, the 2 CB solution will be used (see figure 3).

Double circuit-breaker scheme (2 CB)
Figure 3 – Double circuit-breaker scheme (2 CB)

Go back to Circuit Schemes ↑


4. One-breaker-and-a-half scheme (1.5 CB)

The one-breaker-and-a-half is a compromise between the 2 BB and the 2 CB scheme. This scheme improves the reliability and flexibility because, even in case of loss of a complete busbar, there is no disruption in the power supply of the feeders (see figure 4).

One-breaker-and-a-half scheme (1.5 CB)
Figure 4 – One-breaker-and-a-half scheme (1.5 CB)

Go back to Circuit Schemes ↑


5. 3-phase busbar scheme (3 BB)

For important substations at the nodes of transmission systems for higher voltage levels, the 3-phase busbar scheme is used. It is a common scheme in Germany, utilized at the 380 kV level (see figure 5).

3-phase busbar scheme (3 BB)
Figure 5 – 3-phase busbar scheme (3 BB)

Go back to Circuit Schemes ↑

Reference // Power Engineering Guide by SIEMENS (Download)

Premium Membership

Get access to premium HV/MV/LV technical articles, electrical engineering guides, research studies and much more! It helps you to shape up your technical skills in your everyday life as an electrical engineer.
More Information
author-pic

Edvard Csanyi

Electrical engineer, programmer and founder of EEP. Highly specialized for design of LV/MV switchgears and LV high power busbar trunking (<6300A) in power substations, commercial buildings and industry facilities. Professional in AutoCAD programming.

7 Comments


  1. Khail
    Jan 13, 2020

    Hi Edvard

    Thank your for this web site as it includes so much information. My question is:
    In a transformer 1500 KV the outgoing cables are 11 one core cables
    (1CX630mm for example) 3 for each phase and 2 for neutral . Why the neutral is 2 and not 3

    Thanks a lot


  2. ahsan
    Nov 13, 2019

    its ok sir …..gd work


  3. Sabarish Babu
    May 23, 2016

    Edvard,

    Is the three bus scheme is similar to double main and transfer scheme or any difference is there. because I am seeing from the SLD that buscoupler is connected with both the buses and transfer bus coupler is not available. please clarify.

    regards,
    sabarish babu


  4. Jon-Paul
    Jan 11, 2016

    Dear Edvard,

    Thank You so much for your website. It is such a great aid to me. Thank-You for your time and effort in keeping up to date on the latest applications and technologies. You truly are a asset to the engineering world


  5. Simon Foster
    Jan 04, 2016

    Edvard – Thank you for your excellent work on this portal, I always take a look at what you put on here.

    However I think today you have not done the best job.

    A Single Busbar scheme (3 phase up to 132 kV will usually have a Bus Section CB in the middle
    A Double Busbar system (132kV and above will have Bus Sections and Bus Couplers which effectively form four busbars, carefull selection of feeders and TX’s will usually prevent a power outage for a single busbar fault.
    The 3 phase system you describe, i am not familiar with, and I’m not sure it is any better, aren’t all the arrangements you describe 3 phase??

    Cheers

    Simon (Happy New Year)


    • Edvard
      Jan 04, 2016

      You’re welcome Simon!

      Actually, 3-phase busbar scheme is in this case of higher voltages considered as 3 busbars systems. All previous systems are 3-phase, of course. Sorry for missunderstanding :)


  6. Hamed
    Jan 02, 2016

    we usually use earthing switches without motorize mechanism in MV panels But as i see in your schemes in HV switchgears we do it …why?

Leave a Reply to Edvard

Tell us what you're thinking. We care about your opinion! Please keep in mind that comments are moderated and rel="nofollow" is in use. So, please do not use a spammy keyword or a domain as your name, or it will be deleted. Let's have a professional and meaningful conversation instead. Thanks for dropping by!

sixty two  +    =  sixty six

Learn How to Design Power Systems

Learn to design LV/MV/HV power systems through professional video courses. Lifetime access. Enjoy learning!

Subscribe to Weekly Newsletter

Subscribe to our Weekly Digest newsletter and receive free updates on new technical articles, video courses and guides (PDF).
EEP Academy Courses - A hand crafted cutting-edge electrical engineering knowledge